REPORT TO THE CITY COUNCIL
FROM: RANDALL W. MORRISON, PE, Director
Capital Projects Department
AARON A. AGUIRRE, Director
Parks, After School, Recreation, and Community Services Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
HARLAVPREET S. BRAR, PE, Licensed Professional Engineer
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Roessler Winery Building Project (Council District 4):
1. Affirm the City Manager's finding that Brooks Ransom Associates is uniquely qualified;
2. Approve an agreement for professional architectural and engineering services with Brooks Ransom Associates of Fresno, California for an amount not to exceed $67,500 with an additional $15,000 contingency, for design and construction support services for the historic Roessler Winery Building Project.
Body
RECOMMENDATIONS
Staff recommends City Council approve a consultant services agreement with Brooks Ransom Associates (Brooks), of Fresno, California for an amount not to exceed $67,500 with an additional $15,000 contingency, for design and construction support services for the historic Roessler Winery Building Project and authorize the Capital Projects Director or designee to execute the agreement on behalf of the City.
EXECUTIVE SUMMARY
The City of Fresno Parks, After School, Recreation and Community Services Department (PARCS) proposes to restore and preserve the historic nature of the Roessler Winery Building. The contract for professional engineering design services will be funded using FY24 departmental General Fund appropriations. Council approval of the consultant agreement between the City and Brooks is recommended to facilitate development of plans, cost estimates, and general construction contract documents necessary to complete the project.
BACKGROUND
The PARCS Department proposes ...