Title: Actions pertaining to the Replacement of One Makeup Air Unit and Two Air Handling Units in the Headworks Building at the Fresno-Clovis Regional Wastewater Reclamation Facility (Bid File 12601341) (Council District 3) 1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act Guidelines, Environmental Assessment No. TC00176-HC003 2. Award a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc., of Fresno, California, as the lowest responsive and responsible bidder
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 26-699 Environmental Assessment, 2. 26-699 Bid Evaluation and Fiscal Impact Statement, 3. 26-699 Standardized Construction Contract, 4. 26-699 Vicinity Map, 5. 26-699 Location Map
PREPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

PAUL AMICO, PE, Director
Department of Public Utilities

BY: CASSIE L. SCHOLZ, PE, Assistant Director
Capital Projects Department, Utilities Project Management Division

CHARLES MASTERS, Engineer II
Capital Projects Department, Utilities Project Management Division

SUBJECT
Title
Actions pertaining to the Replacement of One Makeup Air Unit and Two Air Handling Units in the Headworks Building at the Fresno-Clovis Regional Wastewater Reclamation Facility (Bid File 12601341) (Council District 3)
1. Adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act Guidelines, Environmental Assessment No. TC00176-HC003
2. Award a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc., of Fresno, California, as the lowest responsive and responsible bidder

Body
RECOMMENDATIONS

Staff recommends City Council (1) adopt a finding of Categorical Exemption pursuant to Section 15301/Class 1 (Existing Facilities) and Section 15302/Class 2 (Replacement or Reconstruction) of the California Environmental Quality Act (CEQA) Guidelines, Environmental Assessment No. TC00176-HC003, (2) award a Construction Contract in the amount of $833,658 to Strategic Mechanical Inc., as the lowest responsive and responsible bidder for the Replacement of One Makeup Air Unit and Two Air Handling Units in the Headworks Building at the Fresno-Clovis Regional Wastewater Reclamation Facility (Project), and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

The Project will replace critical ventilation units in the Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF) Headworks Building that are original to its 1993 construction...