File #: ID 25-1113    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 8/7/2025 In control: City Council
On agenda: 8/28/2025 Final action:
Title: Approve the Second Amendment to the Consultant Services Agreement with Michael K. Nunley & Associates, Inc., of Fresno, California, to increase the total contract by an amount not to exceed $126,754.00, paid on a time and materials basis with an additional contingency amount not to exceed $19,013.00, for a revised total contract amount not to exceed $229,277.00, and a revised contingency amount not to exceed $34,392.00, and to extend the term of the Agreement to December 31, 2027, for the Design of Booster Pump Replacements at Pump Stations 89A, 150, and 176 Project. (Council District 6)
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 25-1113 Second Amendment to Agreement.pdf, 2. 25-1113 First Amendment to Agreement.pdf, 3. 25-1113 Original Consultant Agreement.pdf, 4. 25-1113 Vicinity Map.pdf, 5. 25-1113 Location Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

PAUL AMICO, PE, Interim Director
Department of Public Utilities

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division

JUSTIN CHAN, PE, Licensed Professional Engineer
Capital Projects Department, Utilities and On-Site Project Management Division

SUBJECT
Title
Approve the Second Amendment to the Consultant Services Agreement with Michael K. Nunley & Associates, Inc., of Fresno, California, to increase the total contract by an amount not to exceed $126,754.00, paid on a time and materials basis with an additional contingency amount not to exceed $19,013.00, for a revised total contract amount not to exceed $229,277.00, and a revised contingency amount not to exceed $34,392.00, and to extend the term of the Agreement to December 31, 2027, for the Design of Booster Pump Replacements at Pump Stations 89A, 150, and 176 Project. (Council District 6)

Body
RECOMMENDATION

Staff recommends that City Council approve the Second Amendment to the Consultant Services Agreement (Agreement) with Michael K. Nunley & Associates, Inc., (Consultant), to increase the total contract by an amount not to exceed $126,754.00, with an additional contingency amount not to exceed $19,013.00, for a revised total contract amount not to exceed $229,277.00 and a revised contingency amount not to exceed $34,392.00, to expand the Consultant's scope of services, and to extend the term of the Agreement to December 31, 2027, for the Design of Booster Pump Replacements at Pump Stations 89A, 150, and 176 Project (Project); and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

On June 10, 2022, the City approved a Consultant Services Agreement with Michael K. Nunley & Associates, Inc., to provide engineering design servic...