SUBJECT
Title
Approve the Fourth Amendment to the Consultant Services Agreement with Electrical Power Systems, Inc., of Fresno, California, to revise the payment terms of the Original Agreement to be paid on a time and materials basis and to increase the total contract by an amount not to exceed $100,207, for a revised total contract amount not to exceed $351,528, paid on a time and materials basis for the Substation Expansion Project at the Fresno-Clovis Regional Wastewater Reclamation Facility. (Council District 3)
Body
RECOMMENDATION
Staff recommends that City Council approve the Fourth Amendment to the Consultant Services Agreement (Agreement) with Electrical Power Systems, Inc. (Consultant), to revise the payment terms of the Original Agreement to be paid on a time and materials basis and to increase the total contract by an amount not to exceed of $100,207, for a revised total contract amount not to exceed $351,528, paid on a time and materials basis, to expand the Consultant's scope of services for the Substation Expansion Project (Project) at the Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF), and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
On October 26, 2018, the City approved a Consultant Services Agreement with Electrical Power Systems, Inc., to provide engineering design services for the design of plans and general construction documents for the Project. The original scope of ...
Click here for full text