File #: ID19-1857    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/5/2019 In control: City Council
On agenda: 7/25/2019 Final action: 7/25/2019
Title: Reject all bids for the Maroa Heights Phase II Water Main Replacement Project - Bid File 3640 (Council District 2 and Fresno County)
Sponsors: Public Works Department
Attachments: 1. 19-1857 BidEvalSigned.pdf, 2. 19-1857 VicinityMap.pdf
REPORT TO THE CITY COUNCIL


July 25, 2019


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

THROUGH: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

BY: SCOTT P. SEHM, PE, Design Services Manager
Public Works Department, Design Services Division

SUBJECT
...Title
Reject all bids for the Maroa Heights Phase II Water Main Replacement Project - Bid File 3640 (Council District 2 and Fresno County)

...Body
RECOMMENDATIONS

Staff recommends that City Council reject all bids for the Maroa Heights Phase II Water Main Replacement Project.

EXECUTIVE SUMMARY

This project will install 8" and 12" water mains, fire hydrants and water services in a former County water district in the vicinity of North Maroa Avenue and West Shaw Avenue. Several water mains are located in easements at the rear or side of the properties and with the proposed project these aging water mains will be abandoned and replaced with new water mains constructed within the street right-of-way and water services relocated accordingly. The new water mains will provide more consistent water pressure, reduce the frequency of service interruptions caused by failures and improve access for maintenance.

The low bidder, Dawson-Mauldin, LLC, was determined to be non-responsive due to not having listed a subcontractor with a valid C-10 license at the time of bid opening. West Valley Construction Company, Inc. submitted the lowest responsive and responsible bid of $3,874,226, which was $574,538 above the low bid. It was determined by the Department of Public Utilities (DPU) that this bid is above the amount budgeted for the project and rejecting all bids and rebidding the project would be the best option to ensure a successful competitive bid process and reasonable construction contract pricing. Staff recommends that Council reject this bid and direct staff to rebid the project.

BACKGROUND

The Maroa Heights Phase II Water Main Replacement ...

Click here for full text