REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
PAUL AMICO, PE, Director
Department of Public Utilities
BY: CASSIE L. SCHOLZ, PE, Assistant Director
Capital Projects Department, Utilities Project Management Division
PATRICIA DIEP, Project Manager
Capital Projects Department, Utilities Project Management Division
SUBJECT
Title
Actions pertaining to the Dewatering Cake Pump Improvement Project (Bid File No. 12600757): (Council District 3)
1. Adopt a finding of Categorical Exemption, pursuant to Section 15301/Class 1 and Section 15302/Class 2 of the California Environmental Quality Act Guidelines
2. Approve the Second Amendment to the Consultant Services Agreement with Black & Veatch Corporation, to increase the total contract by an amount not to exceed $207,758.00, for a revised total contract amount not to exceed $834,205.00 with $11.239.00 in remaining contingency
3. Award a Construction Contract in the amount of $8,800,000.00 to W.M. Lyles Co., of Fresno, California, as the lowest responsive and responsible bidder
Body
RECOMMENDATIONS
Staff recommends that the City Council (1) adopt a finding of Categorical Exemption, pursuant to Section 15301/Class 1 and 15302/Class 2 of the California Environmental Quality Act (CEQA) Guidelines; (2) approve the Second Amendment to the Consultant Services Agreement (Agreement) with Black & Veatch Corporation (Consultant), to increase the total contract by an amount not to exceed $207,758.00, for a revised total contract amount not to exceed $834,205.00 with $11,239.00 in remaining contingency; and (3) award a Construction Contract to W.M. Lyles Co., of Fresno, California (Contractor), in the amount of $8,800,000.00 as the lowest responsive and responsible bidder for the Project, and authorize the Capital Projects Director or designee to sign the standardized Construction Contract on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Pr...