Title: Actions pertaining to the Santa Fe Depot Exterior Americans with Disability Act (ADA) Upgrades project located at 2650 Tulare Street: 1. Adopt Environment Assessment No. SFD0700, dated June 20, 2024, a determination that the proposed project qualifies for categorical exemption as set forth in the California Environmental Quality Act (CEQA) Guidelines Section 15301/Class 1 and Section 15302/Class 2. 2. Approve a Consultant Services Agreement for Professional Engineering Services with Provost and Pritchard Engineering Group, Inc, of Fresno, California, in the amount of $132,500 with a $15,000 contingency, for design, preparation of construction documents, and construction support services for the Santa Fe Depot Phase I Exterior ADA Upgrades project. 3. Authorize the Director of General Services or designee to execute all related documents.
Sponsors: General Services Department
Attachments: 1. Consultant Agreement, 2. Environmental Assessment No. SFD0700
REPORT TO THE CITY COUNCIL


FROM: BRIAN BARR, Director
General Services Department

BY: ROBIN O'MALLEY, Facilities Manager
General Services Department, Facilities Management Division

CRAIG RICCI, Project Manager
General Services Department, Facilities Management Division

SUBJECT
Title
Actions pertaining to the Santa Fe Depot Exterior Americans with Disability Act (ADA) Upgrades project located at 2650 Tulare Street:
1. Adopt Environment Assessment No. SFD0700, dated June 20, 2024, a determination that the proposed project qualifies for categorical exemption as set forth in the California Environmental Quality Act (CEQA) Guidelines Section 15301/Class 1 and Section 15302/Class 2.
2. Approve a Consultant Services Agreement for Professional Engineering Services with Provost and Pritchard Engineering Group, Inc, of Fresno, California, in the amount of $132,500 with a $15,000 contingency, for design, preparation of construction documents, and construction support services for the Santa Fe Depot Phase I Exterior ADA Upgrades project.
3. Authorize the Director of General Services or designee to execute all related documents.

Body
RECOMMENDATION

Actions pertaining to the Santa Fe Depot Exterior ADA Upgrades project located at 2650 Tulare Street:
1. Adopt Environment Assessment No. SFD0700 dated June 20, 2024, a determination that the proposed project qualifies for categorical exemption as set forth in the California Environmental Quality Act (CEQA) Guidelines Section 15301/Class 1 and Section 15302/Class 2.
2. Approve an Agreement for Professional Engineering Services with Provost and Pritchard Engineering Group, Inc. of Fresno, California, in the amount of $132,500 with a $15,000 contingency for the design, preparation of construction documents, and construction support services for the Santa Fe Depot Phase I Exterior ADA Upgrades project.
3. Authorize the Director of General Services or designee to execute all related documents.