File #: ID 25-760    Version: 1 Name:
Type: Action Item Status: Passed
File created: 5/22/2025 In control: City Council
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Approve Phase One of a Progressive Design-Build Contract with Bomel Construction Company Inc., of Irvine, California, in an amount not to exceed $1,612,769.00, for the design support services for the North Fulton Parking Structure Project. (Council District 3)
Sponsors: Capital Projects Department
Attachments: 1. 25-760 Progressive Design-Build Agreement.pdf, 2. 25-760 Vicinity Map.pdf, 3. 25-760 Location Map.pdf
REPORT TO THE CITY COUNCIL


FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director-Capital Projects Department

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division

DALTON BENNETT, Projects Administrator
Capital Projects Department, Utilities and On-Site Project Management Division

SUBJECT
Title
Approve Phase One of a Progressive Design-Build Contract with Bomel Construction Company Inc., of Irvine, California, in an amount not to exceed $1,612,769.00, for the design support services for the North Fulton Parking Structure Project. (Council District 3)

Body
RECOMMENDATION

Staff recommends City Council approve Phase One of a Progressive Design-Build Contract (Contract) with Bomel Construction Company Inc., of Irvine, California, to provide design support services related to the North Fulton Parking Structure Project (Project) in an amount not to exceed $1,612,769.00 with a contingency of $160,000.00, and authorize the Capital Projects Interim Director or designee to execute a final Contract on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

In October 2024, Council approved the use of a Design-Build project delivery method for the North Fulton Parking Structure Project. Staff issued a Request for Qualifications (RFQ) to develop the Project and received five responsible and responsive Statements of Qualifications (SOQ). Based on the evaluation completed by a selections panel, staff recommends approving a Progressive Design-Build agreement with Bomel Construction Company, Inc. (Consultant), for the design of the approximate 234 stall parking structure located at APN 466-206-50T and 466-206-51T within Downtown Fresno.

The Capital Projects Department (CPD) and Consultant shall work collaboratively along with all stakeholders, to design the North Fulton Parking Structure in accordance with the Project's scope and budget. The Project's delivery method take...