REPORT TO THE CITY COUNCIL
FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director - Capital Projects Department
JENNIFER K. CLARK, AICP, Director
Planning and Development Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
HARLAVPREET S. BRAR, Licensed Professional Engineer
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Garage 9 Renovation Project (Bid File No. 12500982) (City Council District 3):
1. Adopt a finding of Categorical Exemption per staff's determination pursuant to section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines, Environmental Assessment No. HG00020, for the Garage 9 Renovation Project;
2. Approve substitution of the listed subcontractor Door Masters, Inc. with Katch Environmental Inc. dba Katch General to self-perform the work associated with doors, frames and hardware;
3. Award a construction contract in the amount of $3,462,279.00, to Katch Environmental Inc. dba Katch General of Fresno, California as the lowest responsive and responsible bidder for the Garage 9 Renovation Project.
Body
RECOMMENDATIONS
Staff recommends the City Council (1) adopt a finding of Categorical Exemption per staff's determination pursuant to Section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines, Environmental Assessment No. HG00020, for the Garage 9 Renovation Project, (2) approve substitution of the listed subcontractor Door Masters, Inc. with Katch Environmental Inc. dba Katch General to self-perform the work associated with doors, frames and hardware, (3) award a construction contract in the amount of $3,462,279.00, to Katch Environmental Inc. of Fresno, California, as the lowest responsive and responsible bidder for the Garage 9 Renovation Project (Project), and authorize the Capital Projects Inte...
Click here for full text