REPORT TO THE CITY COUNCIL
FROM: RANDALL W. MORRISON, PE, Director
Capital Projects Department
BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
PATRICIA DIEP, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Approve the First Amendment to the Professional Engineering Services Agreement with Stearns, Conrad and Schmidt Consulting Engineers, of Long Beach, California to expand the scope of services for the design of the Renewable Natural Gas Diversion into Natural Gas Pipeline Project, increasing the total contract amount by $137,356.58, for a total increased contract amount of $360,115.22, with a remaining contingency of $20,000.00, and extend the agreement term from December 30, 2023 to December 31, 2026 (Council District 3 and unincorporated Fresno County).
Body
RECOMMENDATIONS
Staff recommends the City Council approve the First Amendment to the Consultant Services Agreement (Agreement) with Stearns, Conrad and Schmidt Consulting Engineers (Consultant) to expand the scope of services, increase total contract amount by $137,356.58, for a total increased contract amount of $360,115.22, with a remaining contingency of $20,000, and extend the agreement term from December 30, 2023 to December 31, 2026 for design services for the Renewable Natural Gas (RNG) Diversion into Natural Gas Pipeline Project (Project), and authorize the Capital Projects Director, or designee to sign the amendment on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
On January 12, 2017, the City entered an initial Agreement with the Consultant for a feasibility study and to develop plans for the design of the Project. The initial agreement had an expiration date of January 31, 2018 and subsequent amendments to the original Agreement extended its expiration date ...