REPORT TO THE CITY COUNCIL
November 19, 2020
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
THROUGH: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division
BY: JOHN STANBOULIAN, Public Works Manager
Public Works Department, Traffic Operations Center
SUBJECT
Title
Actions pertaining to the Blackstone Avenue and Abby Street Corridors (from Divisadero Street to Olive Avenue) Intelligent Transportation System (ITS) Adaptive Project - Bid File No. 3759 (Council Districts 3 and 7)
1. Adopt a finding of Categorical Exemption per staff's determination, pursuant to Section 15301(c) Class 1 of the California Environmental Quality Act Guidelines (CEQA)
2. ***RESOLUTION - 42nd Amendment to the Annual Appropriation Resolution No. 2020-159 appropriating $301,000 for the Blackstone Avenue and Abby Street Intelligent Transportation System (ITS) Adaptive Project from McKinley Avenue to Divisadero Street (Requires 5 affirmative votes) (Subject to Mayor's veto)
3. Award a construction contract in the amount of $1,420,012 to Audeamus Inc., dba Sebastian of Fresno, CA, as the lowest responsive and responsible bidder
Body
RECOMMENDATIONS
Staff recommends that City Council (1) adopt a finding of Categorical Exemption per staff determination, pursuant to Section 15301(c) Class 1 of the CEQA Guidelines, (2) adopt the 42nd Amendment to the Annual Appropriation Resolution (AAR) No. 2020-159, (3) award a construction contract with Audeamus Inc., dba Sebastian, of Fresno, CA, in the amount of $1,420,012 as the lowest responsive and responsible bidder, and authorize the Public Works Director or Designee to sign a standardized contract on behalf of the City.
EXECUTIVE SUMMARY
The Blackstone Avenue and Abby Street Adaptive ITS project will expand upon the Blackstone Avenue-Friant Road Adaptive ITS Project (currently under construction) to extend adaptive ITS infrastructure along southern Blackstone Avenue, one of the m...