Legislation Details

File #: ID 22-1846    Version: 1 Name:
Type: Action Item Status: Passed
File created: 11/23/2022 In control: City Council
On agenda: 12/15/2022 Final action: 12/15/2022
Title: Approve the Tenth Amendment to the California High Speed Rail Authority Reimbursement Agreement No. HSR 11-29, which extends the contract end date by 12 months to December 31, 2023 (Council District 1, 2, & 3)
Sponsors: Public Works Department
Attachments: 1. 22-1846 Amendment No 10 to HSR11-29, 2. 22-1846 Vicinity Map
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

JESUS AVITIA, PE, Deputy City Engineer
Public Works Department, Transportation Project Management

SUBJECT
Title
Approve the Tenth Amendment to the California High Speed Rail Authority Reimbursement Agreement No. HSR 11-29, which extends the contract end date by 12 months to December 31, 2023 (Council District 1, 2, & 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Tenth Amendment to the California High Speed Rail Authority (CHSRA) Reimbursement Agreement No. HSR 11-29 (the Agreement) to extend the contract term by 12 months to December 31, 2023 and authorize the Public Works Director or his designee to execute the amendment on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

The Tenth Amendment will extend the term of the Agreement by 12 months, with the new contract end date of December 31, 2023. The amendment will provide for continued reimbursement for the cost of City Staff working on new and existing cooperative agreements and Right of Way functions required for the High-Speed Rail program. Staff will be preparing and reviewing legal descriptions, mapping for Right of Entry, Joint Use Agreements (JUA), Consent for Common Use Agreements (CCUA), Vacations, and dedication packages.

BACKGROUND

On May 3, 2012, City Council approved a Memorandum of Understanding with the CHSRA to develop a series a Cooperative Agreements for the High Speed Rail Project. The CHSRA agreed to reimburse the City for staff cost incurred in developing the Agreements up to $296,000. Reimbursed task included verification of existing right of way, review of proposed design for conformance to City Standards, analysis of utility-HSR conflicts, analysis and verification of utility easements, pre-plan check activities along the HSR corridor and negotiations on ...