Title: Approve Contract Change Order No. 7 in the amount not to exceed $107,830.69, with fifty (50) additional working days, for the installation of two (2) Pacific Gas and Electric Company vaults and the reimbursement of the renewal of the State Water Board Annual Permit Fee with Avison Construction Company, Inc. of Madera, CA for the Transformative Climate Communities Park at MLK Magnet Core (Les Kimber Park) Project - Project ID PW00857 (Bid File 12302905). (Council District 3)
Sponsors: Capital Projects Department, Public Works Department
Attachments: 1. 26-574 Contract Change Order No.7, 2. 26-574 Contract Change Order No. 6, 3. 26-574 Contract Change Order No. 5, 4. 26-574 Contract Change Order No. 4, 5. 26-574 Contract Change Order No. 3, 6. 26-574 Contract Change Order No. 2, 7. 26-574 Contract Change Order No. 1, 8. 26-574 Construction Contract-Avison Construction, 9. 26-574 Vicinity Map
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 7 in the amount not to exceed $107,830.69, with fifty (50) additional working days, for the installation of two (2) Pacific Gas and Electric Company vaults and the reimbursement of the renewal of the State Water Board Annual Permit Fee with Avison Construction Company, Inc. of Madera, CA for the Transformative Climate Communities Park at MLK Magnet Core (Les Kimber Park) Project - Project ID PW00857 (Bid File 12302905). (Council District 3)

Body
RECOMMENDATION

Staff recommends that the City Council approve Contract Change Order No. 7 with Avison Construction Co., Inc. of Madera California which increases the contract amount not to exceed $107,830.69, for a revised contract total not to exceed $11,100,725.93, with fifty (50) additional working days to install two (2) Pacific Gas and Electric Company number seven vaults and reimbursement of the State Water Board Annual Permit Fee at the Transformative Climate Communities (TCC) Park at MLK Magnet Core Project (Les Kimber Park) and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 7 on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On October 19, 2023, a contract was awarded in the amount of $8,646,293.00 to Avison Construction Co., Incorporated of Madera California for the TCC Park at MLK Magnet Core, now known as Les Kimber Park.

City Council approval of Contract Change Order No. 7 in the amount of $107,830.69, with fifty (50) additional working days, will allow for work related to the installation of two (2) Pacific Gas and Electric Company number seven vaults and fifty (50) working days for the redesign, acquisition of materials a...