REPORT TO THE CITY COUNCIL
FROM:	NICHOLAS D. MASCIA, PE, Assistant City Manager
		Interim Director - Capital Projects Department
		AARON A. AGUIRRE, Director
		Parks, After School, Recreation, and Community Services Department
BY:		FRANCISCO V. MAGOS II, PE, Assistant Director
		Capital Projects Department, Utilities and On-Site Project Management Division
		HARLAVPREET S. BRAR, Licensed Professional Engineer
		Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Roeding Park Court Repurposing Project (Bid File No. 12501202), (Council District 3):
1. Adopt a finding of Categorical Exemption per staff's determination pursuant to section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines for the Roeding Park Court Repurposing Project;
2. Award a construction contract in the amount of $1,228,145.00 for the Base Bid plus all three (3) Add Alternates, with Avison Construction, Inc. of Madera, California as the lowest responsive and responsible bidder for the Roeding Park Court Repurposing Project.
Body
RECOMMENDATIONS 
Staff recommends City Council (1) adopt a finding of Categorical Exemption per staff's determination pursuant to Section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines, (2) award a construction contract in the amount of $1,228,145.00 for the Base Bid plus all three (3) Add Alternates, to Avison Construction, Inc. of Madera, California as the lowest responsive and responsible bidder for the Roeding Park Court Repurposing Project (Project), and authorize the Capital Projects Director or designee to sign the standardized construction contract on behalf of the City of Fresno (City).
EXECUTIVE SUMMARY
The Capital Projects Department (CPD) seeks to award a construction contract to Avison Construction, Inc. following a competitive bidding process which identified them as the lowest responsive and responsible bidder in the amount of...