REPORT TO THE CITY COUNCIL
FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director-Capital Projects Department
BROCK D. BUCHE, PE, PLS, Director
Department of Public Utilities
BY: JOSHUA S. RHODES, PE, Assistant Director
Capital Projects Department, Construction Management Division
KELLY YOST, PE, Construction Manager
Capital Projects Department, Construction Management Division
SUBJECT
Title
Approve Contract Change Order No. 3 in the amount of $2,500,000.00 with nine (9) additional working days for completion of domestic water improvements, sanitary sewer improvements, and to increase the Supplemental Work Contract Bid Item with Floyd Johnston Construction Company Incorporated of Fresno, California for the Downtown Redevelopment Grant Water and Sewer Improvements Project - Project ID WM00009 / RC00177. (Bid File 12402356) (Council District 3)
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 3 with Floyd Johnston Construction Company, Inc. of Fresno, California which increases the contract amount by $2,500,000.00, for a revised contract total of $22,110,825.50, with nine (9) additional working days to allow for completion of domestic water improvements, sanitary sewer improvements, and to increase the Supplemental Work Contract Bid Item for the Downtown Redevelopment Grant Water and Sewer Improvements Project and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 3 on the City's behalf.
EXECUTIVE SUMMARY
On June 13, 2024, a contract was awarded in the amount of $18,784,925.50 to Floyd Johnston Construction Company Inc. of Fresno, California for the Downtown Redevelopment Grant Water and Sewer Improvements Project to bring water and sewer facilities to current standards including the replacement of 14,315 linear feet of water mains, 5,576 linear feet of sanitary sewer mains, and rehabilitation of existing sewer an...