File #: ID 23-467    Version: 1 Name:
Type: Action Item Status: Passed
File created: 3/13/2023 In control: City Council
On agenda: 4/27/2023 Final action: 4/27/2023
Title: Actions pertaining to the agreement with Tyler Technologies for implementation and hosting of Financials, Human Capital Management and Utility Billing software: 1. Approve Amendment 2 reallocating $161,400 within the project from unused services. No additional funding is requested. 2. Approve Amendment 3 reallocating $58,400 within the project from unused services. No additional funding is requested.
Sponsors: Information Services Department
Attachments: 1. Amendment 2, 2. Amendment 3, 3. Change Request KOA Hills, 4. Change Request Conversion to IMPL Days
REPORT TO THE CITY COUNCIL


FROM: BRYON HORN, Chief Information Officer
Information Services Department

BY: DENNIS JONES, Systems & Applications Manager
Information Services Department

SUBJECT
Title
Actions pertaining to the agreement with Tyler Technologies for implementation and hosting of Financials, Human Capital Management and Utility Billing software:
1. Approve Amendment 2 reallocating $161,400 within the project from unused services. No additional funding is requested.
2. Approve Amendment 3 reallocating $58,400 within the project from unused services. No additional funding is requested.

Body
RECOMMENDATION

Staff recommends the City Council approve Amendments 2 & 3 to the agreement with Tyler Technologies for implementation and hosting of Financials, Human Capital Management and Utility Billing software. No additional funding is requested.

EXECUTIVE SUMMARY

Amendment 2 removes services designated for KOA Hills (Tyler data conversion partner) which were not needed as the tasks were completed by City staff. This removal allows for the reallocation of $161,400 with $88,800 going toward additional implementation consultant hours and $72,600 toward project travel expenses. This corrects a previously approved project change request with an incorrect amount.

Amendment 3 reallocates $58,400 originally designated for Tyler data conversion related services and will be reallocated toward additional implementation consultant hours for continued work on the Financials and Human Capital Management phases. These services were not needed due to the use of available tools and file imports for data conversion instead. $57,720 will be reallocated for additional consultant hours and $680 toward travel expenses.

BACKGROUND

On January 28, 2021, Council approved an agreement with Tyler Technologies. A first amendment was approved on April 29, 2021. A project change request was approved on February 9, 2023, which reallocated project funds from unneeded services,...

Click here for full text