File #: ID 25-1664    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 11/26/2025 In control: City Council
On agenda: 12/18/2025 Final action:
Title: Actions pertaining to Job Order Contracting for the Airports Department projects for a term of three years with two one-year optional extensions (Bid File 12600201) (District 4, District 3): 1. Award a Job Order Contracting contract for general engineering with Yarbs Grading & Paving Inc. of Fowler, California in an amount not to exceed $3,000,000 for a period of three years; 2. Award a Job Order Contracting contract for general engineering with Terra West Construction, Inc. of Clovis, California in an amount not to exceed $3,000,000 for a period of three years; 3. Award a Job Order Contracting contract for general building construction with Puma Construction of Fresno, California in an amount not to exceed $3,000,000 for a period of three years; 4. Award a Job Order Contracting contract for general building construction with Ardent General, Inc. of Fresno, California in an amount not to exceed $3,000,000 for a period of three years; 5. Award a Job Order Contracting contract for Heatin...
Sponsors: Airports Department
Attachments: 1. 25-1664 Bid Evaluation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


FROM: FRANCISCO PARTIDA, Interim Director of Aviation
Airports Department

BY: CRISTAL DE LA TORRE, Projects Administrator
Airports Department

SUBJECT
Title
Actions pertaining to Job Order Contracting for the Airports Department projects for a term of three years with two one-year optional extensions (Bid File 12600201) (District 4, District 3):
1. Award a Job Order Contracting contract for general engineering with Yarbs Grading & Paving Inc. of Fowler, California in an amount not to exceed $3,000,000 for a period of three years;
2. Award a Job Order Contracting contract for general engineering with Terra West Construction, Inc. of Clovis, California in an amount not to exceed $3,000,000 for a period of three years;
3. Award a Job Order Contracting contract for general building construction with Puma Construction of Fresno, California in an amount not to exceed $3,000,000 for a period of three years;
4. Award a Job Order Contracting contract for general building construction with Ardent General, Inc. of Fresno, California in an amount not to exceed $3,000,000 for a period of three years;
5. Award a Job Order Contracting contract for Heating, Ventilation, Air Conditioning (HVAC) Construction with ACCO Engineered Systems, Inc. of Fresno, California in an amount not to exceed $3,000,000 for a period of three years;
6. Award a Job Order Contracting contract for Heating, Ventilation, Air Conditioning (HVAC) Construction with Strategic Mechanical Inc. of Fresno, California in an amount not to exceed $3,000,000 for a period of three years;
7. Award a Job Order Contracting contract for Electrical Construction with A-C Electric Company of Fresno, California in an amount not to exceed $3,000,000 for a period of three years; and
8. Award a Job Order Contracting contract for Low Voltage Systems with Alpha Omega Data Solutions, Inc. of Los Banos, California in an amount not to exceed $3,000,000 for a period of three years.