REPORT TO THE CITY COUNCIL
October 8, 2015
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
THROUGH: ANDREW J. BENELLI, PE, City Engineer/Assistant Director
Public Works Department, Traffic and Engineering Services Division
CRAIG L. HANSEN, Supervising Real Estate Agent
Public Works Department, Real Estate Services Section
BY: CATHY RODRIGUEZ, Senior Real Estate Agent
Public Works Department, Real Estate Services Section
SUBJECT
Title
Approve the acquisition of 35,046.6 square feet of easement and 48,352 square feet of temporary construction easement of property owned by Barry B. Tayian, Trustee of Barry B. Tayian Trust in the amount of $88,400 (APN 158-181-18) for the construction of thirteen miles of 72-inch diameter pipeline that will convey river water from the Kings River to the City's new Southeast Surface Water Treatment Facility. (City Council District 5)
Body
RECOMMENDATION
Approve the acquisition of 35,046.6 square feet of Easement and 48,352 square feet of Temporary Construction Easement of property owned by Barry B. Tayian, Trustee of Barry B. Tayian Trust in the amount of $88,400 (APN 158-181-18) for the construction of thirteen miles of 72-inch diameter pipeline that will convey river water from the Kings River to the City's new Southeast Surface Water Treatment facility and to authorize the Public Works Director, or designee, to sign all documents necessary to complete the transaction as delegated by the City Manager.
EXECUTIVE SUMMARY
A partial acquisition is required from the subject parcel for the construction of thirteen miles of 72-inch diameter pipeline that will convey river water from the Kings River to the City's new Southeast Surface Water Treatment facility. The value of the acquisition was established by Real Property Analysts, Lawrence D. Hopper, MAI, SRA, AI-GRS. A total of 35,046.6 square feet of Easement and 48,352 square feet of Temp...
Click here for full text