***RESOLUTION - 70th Amendment to the Annual Appropriation Resolution (AAR) No. 2020-159 to appropriate $27,500 for the Blackstone Avenue Smart Mobility Project (Council District 7) (Requires 5 affirmative votes) (Subject to Mayor's veto)
Body
RECOMMENDATION
Staff recommends that the City Council adopt the 70th Amendment to the Annual Appropriation Resolution No. 2020-159 to appropriate $27,500 for the Blackstone Avenue Smart Mobility Project.
EXECUTIVE SUMMARY
Staff is preparing to initiate the design of the Blackstone Avenue Smart Mobility Project, which is funded with a federal Congestion Mitigation and Air Quality Improvement (CMAQ) Program grant and local Measure C funds as the match. Staff recommends Council adopt the 70th Amendment to the AAR in order to provide appropriations in the Public Works FY2021 Capital Budget to sufficiently cover anticipated expenditures for the cost of this project.
BACKGROUND
Staff is seeking Council approval of the attached AAR amendment which will appropriate funding for the Blackstone Avenue Smart Mobility Project. The project is funded via federal CMAQ and local Measure C funds for a total project cost of $2,055,200, with $27,500 of appropriations being requested in the current FY2021 budget year. The remaining project cost of $2,027,700 will be included in future fiscal year capital improvement budgets.
The Blackstone Avenue Smart Mobility Project will construct protected Class IV bicycle facilities in each direction of Blackstone Avenue between Shields Avenue and McKinley Avenue by implementation of a road diet. This project will also install new curb ramps, traffic calming featur...