File #: ID 23-981    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/12/2023 In control: City Council
On agenda: 6/29/2023 Final action: 6/29/2023
Title: Award a construction contract in the amount of $3,260,116 to Granite Construction Company of Fresno, CA, as the lowest responsive and responsible bidder, for the Downtown Fresno Neighborhood Beautification and Cleanup Project (Bid File No. 12302141) (Council Districts 1, 3, & 7)
Sponsors: Public Works Department
Attachments: 1. 23-981 Bid Evaluation, 2. 23-981 Fiscal Impact Statement, 3. 23-981 Vicinity Map, 4. 23-981 Standardized Construction Contract
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

JASON MILLER, PE, Supervising Professional Engineer
Public Works Department, Design Services Section

SUBJECT
Title
Award a construction contract in the amount of $3,260,116 to Granite Construction Company of Fresno, CA, as the lowest responsive and responsible bidder, for the Downtown Fresno Neighborhood Beautification and Cleanup Project (Bid File No. 12302141) (Council Districts 1, 3, & 7)

Body
RECOMMENDATION

Staff recommends the City Council award a construction contract in the amount of $3,260,116 to Granite Construction Company of Fresno, CA, for the Downtown Fresno Neighborhood Beautification and Cleanup Project and authorize the Public Works Director or designee to sign the contract on the City's behalf.

EXECUTIVE SUMMARY

The proposed Downtown Fresno Neighborhood Beautification and Cleanup Project includes both infrastructure and non-infrastructure components. The City seeks to award a construction contract to Granite Construction Company of Fresno, CA, as part the infrastructure portion of the Project on Belmont Avenue from Abby Street to Millbrook Avenue, SR-180 at Fresno Street and SR-180 at First Street. The primary scope of the project includes the reconstruction of median islands along Belmont Avenue, planting of new median and street trees, irrigation, upgrading existing concrete curb ramps to be ADA accessible and improving five existing FAX bus stop locations. The construction contract is for $3,260,116 and is fully funded by the State of California's Clean California Local Grant Program (CCLGP).

BACKGROUND

On January 27, 2022, the City Council authorized the Public Works Department to submit a Grant Application to the California Department of Transportation for the Clean California Local Grant Program (CCLGP); a program created to beautify...

Click here for full text