Fresno Logo
File #: ID18-0748    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/4/2018 In control: City Council
On agenda: 6/28/2018 Final action: 6/28/2018
Title: Actions pertaining to the Herndon Avenue Westbound Widening Project, from Brawley Avenue to Blythe Avenue - Bid File 3606 (Council District 2): 1. Adopt a finding of Categorical Exemption per City of Fresno Environmental Assessment EA-15-028, pursuant to Section 15301/Class 1, Section 15302/Class 2 and Section 15332/Class 32 of the State of California Environmental Quality Act Guidelines for the Herndon Avenue Widening Project, from Brawley Avenue to Blythe Avenue. 2. Award a construction contract in the amount of $845,722.30 to Dave Christian Construction Company, of Fresno, California as the lowest responsive and responsible bidder for the Herndon Avenue Westbound Widening Project, from Brawley Avenue to Blythe Avenue.
Sponsors: Public Works Department
Attachments: 1. 18-0748 Bid Evaluation.pdf, 2. 18-0748 Fiscal Impact Statement.pdf, 3. 18-0748 Vicinity Map.pdf, 4. 18-0748 Standard Contract.pdf
REPORT TO THE CITY COUNCIL



June 28, 2018


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

SCOTT P. SEHM, PE, Design Services Manager
Public Works Department, Design Services Section

SUBJECT
Title
Actions pertaining to the Herndon Avenue Westbound Widening Project, from Brawley Avenue to Blythe Avenue - Bid File 3606 (Council District 2):
1. Adopt a finding of Categorical Exemption per City of Fresno Environmental Assessment EA-15-028, pursuant to Section 15301/Class 1, Section 15302/Class 2 and Section 15332/Class 32 of the State of California Environmental Quality Act Guidelines for the Herndon Avenue Widening Project, from Brawley Avenue to Blythe Avenue.
2. Award a construction contract in the amount of $845,722.30 to Dave Christian Construction Company, of Fresno, California as the lowest responsive and responsible bidder for the Herndon Avenue Westbound Widening Project, from Brawley Avenue to Blythe Avenue.

Body
RECOMMENDATION

Staff recommends the City Council adopt a finding of Categorical Exemption per Environmental Assessment EA-15-028, pursuant to Sections 15301/Class 1, 15302/Class 2 and 15332/Class 32 of the State of California Environmental Quality Act (CEQA) Guidelines, award a construction contract to Dave Christian Construction Company, of Fresno, California in the amount of $845,722.30 as the lowest responsive and responsible bidder for the Herndon Avenue Westbound Widening Project, from Brawley Avenue to Blythe Avenue, and authorize the Public Works Director or designee to sign the contract on behalf of the City.

EXECUTIVE SUMMARY

The proposed project serves to construct the third westbound lane on Herndon Avenue that exists east and west of the project limits, remove an unused left-turn pocket and replace it with landscaped median, construct a section of Class I multipurpose trail and update existing curb ramps to ...

Click here for full text