REPORT TO THE CITY COUNCIL
FROM: HENRY THOMPSON, Director of Aviation
Airports Department
BY: JARRED GARZA, Airports Project Manager
Airports Department
SUBJECT
Title
Actions related to the Terminal Expansion Project at Fresno Yosemite International Airport (Council District 4):
1. Approve Change Order No. 1 for Phase Two Construction of the Progressive Design-Build contract with Q&D Construction as part of the New Terminal Expansion project at Fresno Yosemite International Airport in an amount not to exceed $2,506,060.55 and 140 days.
Body
RECOMMENDATION
Staff recommends that Council authorize the Director of Aviation to execute Contract Change Order (CCO) No. 1 for $2,506,060.55 and 140 days for the Terminal Expansion Project (Project) at Fresno Yosemite International Airport (FAT)
EXECUTIVE SUMMARY
On February 23, 2023, Council awarded the Phase 2 Construction of the Progressive Design Build Contract with Q&D Construction for the New Terminal Expansion project at FAT. This construction phase consists of site excavation and grading, underground utilities, approx. 96,000 sq. ft. terminal building, 2 passenger boarding bridges, and parking lot improvements. During the initial Council award, the Council requested that the new Terminal Arrivals Hall be expanded to properly accommodate the amount of passengers that would flow through the area. The Airports Projects Team and the General Contractor Q&D agreed that could be accomplished and that a return to council would be needed to increase the contract amount to incumber the new change at approx. $2,500,000. After working through the design changes and implementing the requested expansion from Council the project will be able to deliver the expanded arrivals hall accommodating the 2,500 sq. ft. as well as the upgraded arrivals plaza with CCO No.1 for $2,506,060.55 and 140 days. This Change Order will cover the expanded area's full scope to be constructed and time to complete the work, including unfo...