File #: ID16-687    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/1/2016 In control: City Council
On agenda: 6/16/2016 Final action: 6/16/2016
Title: Actions Pertaining to the Kings River Pipeline Project (Bid File 3433), (District 5, Fresno County) 1. Approve an Agreement for Repair of County Roads along the alignment for the raw water pipeline from the Kings River to the Southeast Surface Water Treatment Facility 2. Approve an Addendum to the County Road Encroachment Permit along the alignment for the raw water pipeline from the Kings River to the Southeast Surface Water Treatment Facility
Sponsors: Department of Public Utilities
Attachments: 1. KRP County Roads Agreement.pdf, 2. Addendum KRP
REPORT TO THE CITY COUNCIL


June 16, 2016


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

THROUGH: MICHAEL CARBAJAL, Division Manager
Department of Public Utilities - Water Division

BY: MARTIN WENDELS, Project Manager
Department of Public Utilities

SUBJECT
Title

Actions Pertaining to the Kings River Pipeline Project (Bid File 3433), (District 5, Fresno County)
1. Approve an Agreement for Repair of County Roads along the alignment for the raw water pipeline from the Kings River to the Southeast Surface Water Treatment Facility
2. Approve an Addendum to the County Road Encroachment Permit along the alignment for the raw water pipeline from the Kings River to the Southeast Surface Water Treatment Facility

Body
RECOMMENDATIONS

Staff recommends the City Council approve the Agreement for Repair of County Roads and approve the Addendum to the County Road Encroachment Permit along the alignment for the raw water pipeline from the Kings River to the Southeast Surface Water Treatment Facility for the City of Fresno Kings River Pipeline Project, and finally authorize the Director of Public Utilities or designee to sign the County Agreement on behalf of the City.

EXECUTIVE SUMMARY

On February 26, 2015, the City Council adopted a five-year water utility rate plan to finance the construction of a five-year water capital plan totaling approximately $429 million. The five-year capital plan included the construction of the Kings River Pipeline (Project) to allow the City of Fresno (City) to more effectively use its existing Kings River water allocations by delivering water directly to the Southeast Surface Water Treatment Facility (Facility). A contract has been awarded to Garney Pacific Inc. in the amount of $45,583,750. The County requires an Agreement for Repair of County Roads where the new pipe is installed. Additionally, the County is requiring an Addendum to the County Road Encroachment Permit to ensure construction adheres to the ...