REPORT TO THE CITY COUNCIL
FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director - Capital Projects Department
AARON A. AGUIRRE, Director
Parks, After School, Recreation, and Community Services Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
HARLAVPREET S. BRAR, Licensed Professional Engineer
Capital Projects Department, Utilities and On-Site Project Management Division
SUBJECT
Title
Actions pertaining to the Jaswant Singh Khalra and Regional Sports Complex Cricket Pitch Project (Bid File No. 12500870) (Council District 3):
1. Adopt a finding of Categorical Exemption per staff's determination pursuant to section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines for the Jaswant Singh Khalra Cricket Pitch Project;
2. Adopt a finding of Categorical Exemption per staff's determination pursuant to section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines for the Regional Sports Complex Cricket Pitch Project;
3. Award a construction contract in the amount of $165,785.00, to Juarez Brothers General Engineering, Inc. of Madera, California as the lowest responsive and responsible bidder for the Jaswant Singh Khalra and Regional Sports Complex Cricket Pitch Project.
Body
RECOMMENDATIONS
Staff recommends the City Council (1) adopt a finding of Categorical Exemption per staff's determination pursuant to Section 15301/Class 1 of the California Environmental Quality Act (CEQA) Guidelines for the Jaswant Singh Khalra Cricket Pitch Project, (2) adopt a finding of Categorical Exemption per staff's determination pursuant to section 15301/Class 1 of the CEQA Guidelines for the Regional Sports Complex Cricket Pitch Project, (3) award a construction contract in the amount of $165,785.00 to Juarez Brothers General Engineering, Inc. of Madera, California, as the lowest responsive and responsible bidder for...
Click here for full text