REPORT TO THE CITY COUNCIL
FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department
AARON A. AGUIRRE, Director
Parks, After School, Recreation and Community Services Department
BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division
RICHARD L. MADRIGAL, Project Manager
Capital Projects Department, Utilities and On-Site Project Management
SUBJECT
Title
Approve Contract Change Order No. 4 with American Paving Co., Inc., of Fresno, California in the amount not to exceed $629,496.67 with two hundred (200) additional working days for the Southeast Fresno Sports Complex Project. (Bid File 12402799) (Council District 5)
Body
RECOMMENDATION
Staff recommends that the City Council approve Contract Change Order No. 4 with American Paving Co., Inc., of Fresno, California in the amount not to exceed $629,496.67 with two hundred (200) additional working days for construction of concrete trail, plantings, site furniture, and street frontage improvements along Geary Street for the Southeast Fresno Sports Complex Project, and authorize the Capital Projects Department Director, or designee, to sign this Contract Change Order No. 4 on behalf of the City of Fresno.
EXECUTIVE SUMMARY
On October 10, 2024, the City of Fresno awarded a contract in the amount of $9,653,846.35 to American Paving Co., Inc., of Fresno, California for the South Peach Park Project, now known as Southeast Fresno Sports Complex. The Project includes construction of the first 10 acres of a 49-acre park, excluding a 20-foot strip of land along Geary Street which was not yet owned by the City of Fresno but acquired in January 2025.
City Council approval of the proposed Contract Change Order No. 4 in the amount not to exceed $629,496.67, with two hundred (200) additional working days, will enable construction of a concrete trail, additional plantings, site furniture, a masonry buffer wall, and s...