On agenda: 9/25/2025 Final action: 9/25/2025
Title: Approve the Second Amendment to the Consultant Services Agreement with AECOM Technical Services, Inc., of Fresno, California, to increase the total contract by an amount not to exceed $32,463.00, paid on a time and materials basis, for a revised total contract amount not to exceed $265,663.00, with a remaining contingency amount not to exceed $20,000.00, and extend the term of the Agreement to December 31, 2028, for the engineering design services related to the Wellhead Treatment Improvements at Pump Station 101A Project. (Council District 7)
Sponsors: Capital Projects Department, Department of Public Utilities
Attachments: 1. 25-1215 Second Amendment to Agreement.pdf, 2. 25-1215 First Amendment to Agreement.pdf, 3. 25-1215 Original Consultant Agreement.pdf, 4. 25-1215 Vicinity Map.pdf, 5. 25-1215 Location Map.pdf
REPORT TO THE CITY COUNCIL


FROM: DENIX D. ANBIAH, PE, Director
Capital Projects Department

PAUL AMICO, PE, Interim Director
Department of Public Utilities

BY: FRANCISCO V. MAGOS II, PE, Assistant Director
Capital Projects Department, Utilities and On-Site Project Management Division

ANITA LUERA, Project Manager
Capital Projects Department, Utilities and On-Site Project Management Division

SUBJECT
Title
Approve the Second Amendment to the Consultant Services Agreement with AECOM Technical Services, Inc., of Fresno, California, to increase the total contract by an amount not to exceed $32,463.00, paid on a time and materials basis, for a revised total contract amount not to exceed $265,663.00, with a remaining contingency amount not to exceed $20,000.00, and extend the term of the Agreement to December 31, 2028, for the engineering design services related to the Wellhead Treatment Improvements at Pump Station 101A Project. (Council District 7)

Body
RECOMMENDATION

Staff recommends that City Council approve the Second Amendment to the Consultant Services Agreement (Agreement) with AECOM Technical Services, Inc. (Consultant) of Fresno, California, to increase the total contract by an amount not to exceed $32,463 paid on a time and materials basis, for a revised total contract amount not to exceed $265,663, with a remaining contingency amount not to exceed $20,000, and extend the term of the Agreement to December 31, 2028, for additional design services related to the Wellhead Treatment Improvements at Pump Station 101A Project (Project); and authorize the Capital Projects Director or designee to sign and execute all documents on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

On June 10, 2022, the Department of Public Utilities (DPU) entered into a Consultant Services Agreement with AECOM Technical Services, Inc. of Fresno, California, in the amount of $233,200 with a contingency amount not to exceed $20,000 to provide engineering de...