Fresno Logo
File #: ID 23-257    Version: 1 Name:
Type: Action Item Status: Passed
File created: 2/1/2023 In control: City Council
On agenda: 2/23/2023 Final action: 2/23/2023
Title: Approve Contract Change Order No. 03 with Avison Construction extending the date of completion to May 1, 2023 for the Shields Bankside Trail Project ID PW00725 (Council District 7)
Sponsors: Public Works Department
Attachments: 1. 23-257 Contract Change Order No. 03
REPORT TO THE CITY COUNCIL



FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Construction Management Division

KELLY YOST, PE Construction Manager
Public Works Department, Construction Management Division

SUBJECT
Title
Approve Contract Change Order No. 03 with Avison Construction extending the date of completion to May 1, 2023 for the Shields Bankside Trail Project ID PW00725 (Council District 7)

Body
RECOMMENDATION

Staff recommends that City Council approve Contract Change Order No. 03 in the amount of $0.00 on behalf of the City of Fresno to Avison Construction to increase Contract Time by forty-five (45) working days.

EXECUTIVE SUMMARY

The purpose of the change order is to allow the Contractor forty-five additional working days due to delays with PG&E pole relocations, a new water service connection that had not been identified on the construction drawings, and extensive irrigation wire theft that occurred during construction, delaying the Contractor from completing the project. The change order involves additional time but no additional cost to the City.

BACKGROUND

On September 1, 2016, the City Council approved the funding agreement to allow Measure "C" funding to be used for the design and construction of the Midtown Trail (then referred to as the "Metro Trail"). The Midtown Trail was split into five segments to be designed and constructed as stand-alone projects.

The Shields Avenue Bankside Trail Project, Shields Avenue from First Street to Fresno Street, is Segment 2 of the Midtown Trail program, a planned 7 mile pedestrian and cycle multipurpose trail, which will ultimately provide connectivity between the Fresno Area Express hub at Manchester Center and the Clovis Old Town Trail. The planned corridor will follow the Herndon Canal alignment along Shields Avenue, from Shields Avenue and First Street to McKinley Avenue, then along the Mill Creek...