Fresno Logo
File #: ID 20-001562    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 11/10/2020 In control: City Council
On agenda: 12/3/2020 Final action: 12/3/2020
Title: Approve a substitution of a listed Subcontractor JT2, Inc. dba Todd Companies for Fresno Fire Station No. 18 (Council District 1)
Sponsors: Public Works Department
Attachments: 1. 20-001562 Contractor's Request for Substitution Letter
REPORT TO THE CITY COUNCIL


December 3, 2020


FROM: SCOTT L. MOZIER, PE TE, Director
Public Works Department

THROUGH: WILLIAM C. HERR, Assistant Director
Public Works Department, Facilities and Construction Management Divisions

BY: KARL LENHOF, Chief Engineering Inspector
Public Works Department, Construction Management Divisions

SUBJECT
Title
Approve a substitution of a listed Subcontractor JT2, Inc. dba Todd Companies for Fresno Fire Station No. 18 (Council District 1)

Body
RECOMMENDATION

It is recommended that the City Council approve the request from Klassen Corporation (Klassen), to substitute JT2, Inc. dba Todd Companies (Todd Companies) and utilize Total Concrete Services, Incorporated (Total Concrete), for the cast in-place concrete portion of this project.

EXECUTIVE SUMMARY

Klassen, the General Contractor who was awarded the referenced project, has requested to substitute Todd Companies, who is listed in the bid documents as performing the cast in-place concrete portion of the project. In accordance with the bid documents, Klassen listed Todd Companies for the cast in-place concrete portion of the project because the work exceeds one-half of one percent of the total contract amount.

Klassen notified the City by letter dated October 1, 2020, that their Subcontractor, Todd Companies after having a reasonable opportunity to do so has failed or refused to execute a written subcontract.
Klassen is asking that they be allowed to use Total Concrete to perform the cast in-place concrete portion. This action requires Council approval because Public Contract Code section 4107 requires consent of the awarding authority to a request by a prime contractor for a substitution of a subcontractor.

BACKGROUND

On November 14, 2019, a contract was awarded in the amount of $6,260,000 to Klassen, for the Fresno Fire Station No. 18 Project; the Notice to Proceed was issued with a start date of February 18, 2020.

In the original proposal, Todd Comp...

Click here for full text