REPORT TO THE CITY COUNCIL
July 16, 2015
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
TRHOUGH: ANDREW J. BENELLI, PE, City Engineer/Assistant Director
Public Works Department, Traffic and Engineering Services Division
BY: JONATHAN BARTEL, Supervising Engineering Technician
Public Works Department, Traffic and Engineering Services Division
SUBJECT
Title
RESOLUTION - Approving the Final Map of Tract No. 6063 and accepting dedicated public uses offered therein-Southeast corner of N. Friant Road and E. Copper Avenue (Council District 6)
Body
RECOMMENDATION
Staff recommends the City Council adopt a resolution approving the Final Map of Tract No. 6063 and accepting the dedicated public uses offered therein.
EXECUTIVE SUMMARY
The Subdivider, Copper Park, LLC, a California Limited Liability Company, (Farid Assemi, Manager), has filed for approval, the Final Map of Tract No. 6063, for a 10-lot single family residential planned unit development, located on the Southeast corner of North Friant Road and East Copper Avenue on 1.86 acres.
BACKGROUND
The Fresno City Planning Commission on July 2, 2014 adopted Resolution No. 13294 approving Vesting Tentative Map No. 6063 (Tentative Map) for a 10-lot single family residential planned unit development on 1.86 acres at an overall density of 5.61 units per acre. The Fresno City Planning Commission on January 15, 2014 adopted Resolution No. 13295 approving Conditional Use Permit Application No. C-14-018 authorizing the development of a 10-lot single family residential planned unit development with modified property development standards and public street access. The Tentative Map was approved consistent with the 2025 General Plan and the Woodward Park Community Plan to comply with the provisions of the Subdivision Map Act. The approval of Vesting Tentative Map No. 6063 will expire on July 2, 2016. The Final Map is technically correct and conforms to the approved Tentative Map, the Subdivision Map Act and the Fresno Municipal Code. The provisions of Section 66474.1 of the Subdivision Map Act require a final map that is in substantial compliance with the approved tentative map to be approved by the City Council.
The Subdivider has satisfied all other conditions of approval and has paid the miscellaneous and development impact fees due as a condition of approval for the Final Map in the amount of $38,642.40. Covenants have been executed to defer eligible development impact fees totaling $134,414.09 to the time of issuance of building permit and final occupancy of each unit, for annual CFD-11 assessment notification, for special solid waste disposal services and for acknowledging right to farm law. The City Attorney’s Office has approved all documents as to form.
Maintenance District: A condition of approval of the Tentative Map is to maintain all concrete curbs and gutters, sidewalks, interior local street paving, street name signage and street lights along East Carnoustie Avenue within the Final Map in accordance with the adopted standards of the City. The Subdivider has satisfied the maintenance requirement by annexing the subdivision into the City’s Community Facility District No. 11 (CFD-11) on October 2, 2014.
The Subdivider has executed the covenant for Maintenance of Certain Improvements and is required to provide every prospective purchaser of each lot of the subdivision the “Notice of Special Tax”, in accordance with the provision of Section 53341.5 of the California Government Code. The maximum annual assessment is $148.00 per lot with an annual 3% adjustment plus the increase, if any, in the construction cost index for the San Francisco Region.
ENVIRONMENTAL FINDINGS
Pursuant to CEQA Guidelines Section 15268(b)(3), approval of final subdivision maps is a ministerial action and is exempt from the requirements of CEQA.
LOCAL PREFERENCE
Local preference was not considered because this resolution does not include a bid or award of a construction or services contract.
FISCAL IMPACT
The Final Map is located in Council District 6. There will be no impact to the City’s General Fund. Approval by the Council will result in timely deliverance of the review and processing of the Final Map as is reasonably expected by the Subdivider. Prudent financial management is demonstrated by the expeditious completion of this Final Map inasmuch as the Subdivider has paid the City a fee for the processing of this Final Map and that fee is, in turn, funding the respective operations of the Public Works Department.
Attachments:
Resolution
Final Map of Tract No. 6063