File #: ID#15-961    Version: 1 Name:
Type: Action Item Status: Passed
File created: 10/21/2015 In control: City Council
On agenda: 11/19/2015 Final action: 11/19/2015
Title: Approve the acquisition of 39,536 square feet of easement on property (APN 330-021-03) owned by Joe Rebella Jr. and Kathleen R. Rebella in the amount of $66,700 for the construction of new sanitary sewer lines within East Avenue, Orange Avenue, Cedar Avenue, Malaga Avenue and Central Avenue. (Council District 3)
Sponsors: Public Works Department
Attachments: 1. APN 33002103Vicinitymap.pdf
REPORT TO THE CITY COUNCIL


November 19, 2015


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

THROUGH: ANDREW J. BENELLI, PE, City Engineer/Assistant Director
Public Works Department, Traffic and Engineering Services Division

CRAIG L. HANSEN, Supervising Real Estate Agent
Public Works Department, Real Estate Services Section

BY: CATHY RODRIGUEZ, Senior Real Estate Agent
Public Works Department, Real Estate Services Section


SUBJECT
Title

Approve the acquisition of 39,536 square feet of easement on property (APN 330-021-03) owned by Joe Rebella Jr. and Kathleen R. Rebella in the amount of $66,700 for the construction of new sanitary sewer lines within East Avenue, Orange Avenue, Cedar Avenue, Malaga Avenue and Central Avenue. (Council District 3)

Body
RECOMMENDATION

1. Approve the acquisition of 39,536 square feet of easement on property (APN 330-021-03) owned by Joe Rebella Jr. and Kathleen R. Rebella in the amount of $66,700 for the construction of new sanitary sewer lines within East Avenue, Orange Avenue, Cedar Avenue, Malaga Avenue and Central Avenue.
2. Authorize the Public Works Director, or designee, to sign all documents necessary to complete the transaction.

EXECUTIVE SUMMARY

A partial acquisition is required from the subject parcel (APN 330-021-03) for the construction of new sanitary sewer lines and fiber optic conduit along East Avenue, Orange Avenue, Cedar Avenue, Malaga Avenue and Central Avenue. The project necessitates the acquisition of an easement totaling 39,536 square feet in order for the sewer main and fiber optic conduit to be installed. The value of the acquisition was established by Real Property Analysts, Lawrence D. Hopper, MAI. Staff engaged the property owners on September 9, 2015 and presented the First Written Offer. The owners accepted the offer at the appraised value of $66,700.

BACKGROUND

The Department of Public Utiliti...