Fresno Logo
File #: ID16-741    Version: 1 Name:
Type: Action Item Status: Passed
File created: 6/9/2016 In control: City Council
On agenda: 6/30/2016 Final action: 6/30/2016
Title: Actions pertaining to sewer rehabilitation in Church Avenue (Council District 3 and Fresno County) 1. Adopt findings of Categorical Exemption of Class 1, pursuant to Section 15301(b) (Existing facilities of both investor and publicly-owned utilities) and Class 2, pursuant to Section 15302(c) (Replacement or reconstruction) of the California Environmental Quality Act Guidelines, and 2. Award a construction contract in the amount of $1,730,760 to SAK Construction, LLC of O'Fallon Missouri
Sponsors: Department of Public Utilities
Attachments: 1. 2016-06-30 Sign BidEval for Church Ave.pdf, 2. 2016-06-30 Church Ave vicinity map.pdf, 3. 2016-06-30 Sample contract for Church Ave
REPORT TO THE CITY COUNCIL


June 30, 2016


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

THROUGH: KEVIN L. NORGAARD, PE, Supervising Professional Engineer
Department of Public Utilities

BY: PATRICIA DIEP, Supervising Engineering Technician
Department of Public Utilities - Wastewater Management Division

SUBJECT
Title

Actions pertaining to sewer rehabilitation in Church Avenue (Council District 3 and Fresno County)
1. Adopt findings of Categorical Exemption of Class 1, pursuant to Section 15301(b) (Existing facilities of both investor and publicly-owned utilities) and Class 2, pursuant to Section 15302(c) (Replacement or reconstruction) of the California Environmental Quality Act Guidelines, and
2. Award a construction contract in the amount of $1,730,760 to SAK Construction, LLC of O'Fallon Missouri

Body
RECOMMENDATIONS

Staff recommends that Council adopt findings of Categorical Exemption of Class 1 pursuant to Section 15301(b) (Existing facilities of both investor and publicly-owned utilities) and Class 2, pursuant to Section 15302(c) (Replacement or reconstruction) of the California Environmental Quality Act (CEQA) Guidelines and approve the construction contract award in the amount of $1,730,760 to SAK Construction, LLC of O'Fallon Missouri.

EXECUTIVE SUMMARY

The Department of Public Utilities, Wastewater Management Division is seeking to award a construction contract to SAK Construction, LLC for the rehabilitation of a sewer in Church Avenue between Fruit Avenue and Martin Luther King Jr Boulevard. The existing sewer is standard concrete pipe and in need of rehabilitation. The sewer rehabilitation project is necessary to remedy current structural deficiencies and increase the design life of the pipe. Staff is seeking to award a contract in the amount of $1,730,760 to SAK Construction, LLC.

BACKGROUND

In the 2014 Wastewater Collection System Master Plan update, this sewer was identified to be rehabilitated ...