REPORT TO THE CITY COUNCIL
October 20, 2016
FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities
THROUGH: MICHAEL CARBAJAL, Division Manager
Department of Public Utilities - Water Division
BY: GLENN A. KNAPP, Professional Engineer
Department of Public Utilities - Water Division
SUBJECT
Title
Actions pertaining to Supervisory Control and Data Acquisition and Programmable Logic Control Software Installation and Integration for the City of Fresno's Southeast Surface Water Treatment Facility and Kings River Pipeline Project (All Districts):
1. Reject all bids for Supervisory Control and Data Acquisition, and Programmable Logic Control Software Installation and Integration services for the City of Fresno's Southeast Surface Water Treatment Facility and Kings River Pipeline Project. (Bid File 3472).
2. Approve Project Change Order No. 5 to WM Lyles Company in the amount of $2,493,750 for Supervisory Control and Data Acquisition and Programmable Logic Control Software Installation and Integration Services for the City of Fresno's Southeast Surface Water Treatment Facility and Kings River Pipeline Project.
3. Approve a one-time extension of the current limits of Construction Contract Change Order Authority for the City of Fresno's Chief Administrative Officer to $3,500,000 as related to the Southeast Surface Water Treatment Facility.
Body
RECOMMENDATIONS
Staff recommends that Council reject all submitted bids, approve project Change Order No. 5 (CO#5) as related to Supervisory Control and Data Acquisition (SCADA) and Programmable Logic Control (PLC) software installation and integration services for the City of Fresno's Southeast Surface Water Treatment Facility (Facility), and Kings River Pipeline (Pipeline) Project, and approve a one-time extension of the current limits of Construction Contract Change Order Authority for the City's Chief Administrative Officer to $3,500,000 for the Facility.
EXECUTIVE SUMMARY
In July 2016, a singl...
Click here for full text