File #: ID16-1459    Version: 1 Name:
Type: Action Item Status: Passed
File created: 11/30/2016 In control: City Council
On agenda: 12/15/2016 Final action: 12/15/2016
Title: Approve Seventh Amendment to the Consultant Services Agreement with Provost & Pritchard Engineering Group, for $201,000 to provide Construction Phase and General Construction Contract Administration Services and a partial redesign for the City of Fresno's Friant-Kern Canal Pipeline Project (Council District 6, and the County of Fresno).
Sponsors: Department of Public Utilities
Attachments: 1. Amendment 7.pdf
REPORT TO THE CITY COUNCIL


December 15, 2016


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

THROUGH: MICHAEL CARBAJAL, Planning Manager
Department of Public Utilities - Water Division

BY: DEJAN PAVIC, Professional Engineer
Department of Public Utilities - Water Division

SUBJECT
Title

Approve Seventh Amendment to the Consultant Services Agreement with Provost & Pritchard Engineering Group, for $201,000 to provide Construction Phase and General Construction Contract Administration Services and a partial redesign for the City of Fresno's Friant-Kern Canal Pipeline Project (Council District 6, and the County of Fresno).

Body
RECOMMENDATIONS

Staff recommends that City Council:

1. Approve Seventh Amendment to the Consultant Services Agreement with Provost & Pritchard Engineering Group, for $201,000 to provide Construction Phase and General Construction Contract Administration Services and a partial redesign for the City of Fresno's Friant-Kern Canal Pipeline Project.

2. Authorize the Director of Public Utilities, or designee, to sign the Amendment on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On April 10, 2007, the Fresno City Council approved an Agreement with Provost & Pritchard Engineering Group (Provost & Pritchard) to provide the following services for the Friant-Kern Canal Raw Water Pipeline (Project):

Part 1: Alignment Comparison and Schematic Design Phase
Part 2: Public Participation Assistance Phase
Part 3: Environmental Services
Part 4: Right-of-Way Acquisition Phase
Part 5: Design Development Phase
Part 6: Construction Document Phase
Part 7: Bidding Phase
Part 8: Construction Phase and General Construction Contract Administration

The proposed pipeline will deliver the City's Central Valley Project (CVP) surface water to the Northeast Surface Water Treatment Facility (Facility). Parts 1 through 7 of the agreement are now complete and the general construction contract was awarded by the City Council on Apri...

Click here for full text