REPORT TO THE CITY COUNCIL
December 15, 2016
FROM: SCOTT L. MOZIER, Director
Public Works Department
BY: ROBERT N. ANDERSEN, PE, Assistant Director
Public Works Department - Capital Management Division
DEBBIE BERNARD, Project Manager
Public Works Department - Facilities Management Division
SUBJECT
Title
Reject all bids for the Memorial Auditorium Stage Grid Ladder and Guardrail project (Bid File No. 3478) (Council District 3)
Body
RECOMMENDATION
Staff recommends that Council reject all bids received for the Memorial Auditorium Stage Grid Ladder and Guardrail project.
EXECUTIVE SUMMARY
Plans and specifications were prepared and advertised for bids. One sealed bid proposal was received that was significantly above the engineer's estimate. As a result of subsequent discussions, and the realization there are likely other deferred capital needs, the PARCS Department and Public Works Department will be commissioning a facility assessment of Memorial Auditorium that will be completed prior to the end of the fiscal year.
BACKGROUND
The Veteran's Memorial Auditorium was built in 1935 and includes a full performance stage with ladder-accessible 60'-up fly-grid and associated counter-weighted lineset rigging system. On July 10, 2013, the City of Fresno entered into an agreement with TAM+CZ for Phase I of the Memorial Auditorium Stage Rigging System upgrade which entailed an Inspection and Report of the Stage Rigging System condition. On June 9, 2014, the Memorial Auditorium Stage Rigging System Report was issued listing several items in need of repairs and/or upgrades, including the stage grid access ladder and a guardrail system.
On September 30, 2014, the City of Fresno entered into an agreement with TAM+CZ for the preparation of plans and general construction contract documents for the construction of the Memorial Auditorium Stage Grid Ladder and Guardrail. Plans and specifications were developed and a Notice Inviting Bids was pub...
Click here for full text