File #: ID17-0030    Version: 1 Name:
Type: Action Item Status: Passed
File created: 12/22/2016 In control: City Council
On agenda: 1/12/2017 Final action: 1/12/2017
Title: Actions Pertaining to the Engineering Services to divert Renewable Natural Gas into the Natural Gas pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Council District 3) 1. ***RESOLUTION - 12th Amendment to the Annual Appropriation Resolution No. 2016-118 appropriating $637,000 for engineering services to divert renewable natural gas into the natural gas pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Requires 5 affirmative votes) 2. Award a professional engineering services contract for $592,000, with $25,000 contingency, to Stearns, Conrad and Schmidt Consulting Engineers Incorporated of Long Beach, California
Sponsors: Department of Public Utilities
Attachments: 1. 17 12th Eng Svcs Divert Nat Gas SAM 1-2-17.pdf, 2. Agreement.pdf, 3. 2017-01-12 SCS Pipeline Injection Contract Fiscal Impact.pdf, 4. 2017-01-12 SCS Pipeline Injection Contract VICINITY MAP.pdf
REPORT TO THE CITY COUNCIL


January 12, 2017


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

BY: KEVIN L. NORGAARD, PE, Supervising Professional Engineer
Department of Public Utilities - Wastewater Management Division


SUBJECT
Title

Actions Pertaining to the Engineering Services to divert Renewable Natural Gas into the Natural Gas pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Council District 3)
1. ***RESOLUTION - 12th Amendment to the Annual Appropriation Resolution No. 2016-118 appropriating $637,000 for engineering services to divert renewable natural gas into the natural gas pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Requires 5 affirmative votes)
2. Award a professional engineering services contract for $592,000, with $25,000 contingency, to Stearns, Conrad and Schmidt Consulting Engineers Incorporated of Long Beach, California

Body
RECOMMENDATION

Staff recommends the Council appropriate the project funding and approve the agreement award to Stearns, Conrad and Schmidt Consulting Engineers Inc. (Stearns), for the feasibility study and if appropriate the design necessary to divert and inject renewable natural gas into the natural gas distribution pipeline at the Fresno/Clovis Regional Wastewater Reclamation Facility (Facility).

EXECUTIVE SUMMARY

The City of Fresno has successfully operated the anaerobic digestion processes at the Facility for approximately sixty years. The purpose of this project is to provide additional redundancies for the utilization of the digester gases generated as part of the wastewater solids processing. This project will first confirm the financial and engineering feasibility to clean the gas and inject it back into the state natural gas distribution pipe system. Part of the feasibility study will include the investigation of the sale of Renewable Natural Gas (RNG).

BACKGROUND

The Facility has successfully operated an anaerobic digestion...

Click here for full text