Fresno Logo
File #: ID17-1318    Version: 1 Name:
Type: Action Item Status: Passed
File created: 9/18/2017 In control: City Council
On agenda: 10/19/2017 Final action: 10/19/2017
Title: Actions related to Senate Bill 1 (SB1) Road Maintenance and Rehabilitation Account (RMRA) revenues: 1. Review the Public Works Department's current five-year capital improvement plan 2. Approve the Public Works Department's SB1 street project list for FY2018 3. Approve a priority list for SB1 expenditures for FY2019 through FY2022
Sponsors: Public Works Department
Attachments: 1. Attachment A - SB1 Street Projects FY18.pdf, 2. Attachment B - Current DPW 5 year Capital Program.pdf, 3. Attachment C - Priority List SB1 FY2019 thru FY2022.pdf, 4. Attachment D1 - 2017-signal-priority-list.pdf, 5. Attachment D2 - 2017-Left-Turn-Phasing-priority-List.pdf, 6. Attachment E - ATP Chapter 5 Planned Networks.pdf, 7. Attachment F - ATP Projects Cost Estimates.pdf, 8. Attachment G - Final_LSR_Program_Reporting_Guidelines.pdf
REPORT TO THE CITY COUNCIL



October 19, 2017


FROM: SCOTT MOZIER, PE, Director
Public Works Department

BY: ANDREW J BENELLI, PE, City Engineer / Assistant Director
Public Works Department

BRIAN RUSSELL, Public Works Manager
Public Works Department, Street Maintenance Division

SUBJECT
Title
Actions related to Senate Bill 1 (SB1) Road Maintenance and Rehabilitation Account (RMRA) revenues:
1. Review the Public Works Department's current five-year capital improvement plan
2. Approve the Public Works Department's SB1 street project list for FY2018
3. Approve a priority list for SB1 expenditures for FY2019 through FY2022

Body
RECOMMENDATION

Staff recommends the Council review the current five-year capital improvement plan as contained in the adopted FY2018 budget document, approve the Department's SB1 street project list for FY2018 and approve a priority list for SB1 expenditures for FY2019 through FY2022.

EXECUTIVE SUMMARY

During the June 2017 budget hearings, the Council requested a five-year plan for street projects, including the new revenue from SB1, the Road Repair and Accountability Act of 2017. In order to receive SB1 revenue, all projects proposed for funding must be included in the City's adopted budget. Furthermore the project list adopted by the Council must include description, locations, schedules for completion and estimated useful life of the improvement. Staff also recommends the Council review the current five-year capital program as included in the FY2018 budget document, which incorporates all known and projected revenue sources. However, given that the five-year capital program did not assume SB1 revenues for FY2019 through FY2022, staff recommends the Council approve the attached priority list for SB1 expenditures for those four years.

The current five-year capital program incorporates all known revenue streams and future year transportation grants the City has already been awarded. In addition to street maintenance pri...