Title: Actions pertaining to the Fulton Street Reconstruction Project construction contract with American Paving Company of Fresno, California (Council District 3) 1. Approve Contract Change Order No. 64, which increases the contract amount by $52,540.06 2. Approve Contract Change Order No. 66, which decreases the contract amount by $33,830.41 3. Approve Contract Change Order No. 67, which increases the contract amount by $28,600.00 4. Approve Contract Change Order No. 68, which increases the contract amount by $26,955.60 5. Approve Contract Change Order No. 69, which increases the contract amount by $75,000.00 6. Approve Contract Change Order No. 70, which decreases the contract amount by $7,695.32
Sponsors: Public Works Department
Attachments: 1. 17-1632 Fulton Street - Contract Change Order No. 64.pdf, 2. 17-1632 Fulton Street - Contract Change Order No. 66.pdf, 3. 17-1632 Fulton Street - Contract Change Order No. 67.pdf, 4. 17-1632 Fulton Street - Contract Change Order No. 68.pdf, 5. 17-1632 Fulton Street - Contract Change Order No. 69.pdf, 6. 17-1632 Fulton Street - Contract Change Order No. 70.pdf
REPORT TO THE CITY COUNCIL


December 7, 2017


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division


SUBJECT
Title
Actions pertaining to the Fulton Street Reconstruction Project construction contract with American Paving Company of Fresno, California (Council District 3)
1. Approve Contract Change Order No. 64, which increases the contract amount by $52,540.06
2. Approve Contract Change Order No. 66, which decreases the contract amount by $33,830.41
3. Approve Contract Change Order No. 67, which increases the contract amount by $28,600.00
4. Approve Contract Change Order No. 68, which increases the contract amount by $26,955.60
5. Approve Contract Change Order No. 69, which increases the contract amount by $75,000.00
6. Approve Contract Change Order No. 70, which decreases the contract amount by $7,695.32

Body
RECOMMENDATION

Staff recommends that City Council approve Contract Change Orders No. 64, 66, 67, 68, 69 and 70 with American Paving Company of Fresno, California for a total increase in contract amount of $141,569.93 for the Fulton Street Reconstruction Project.

EXECUTIVE SUMMARY

The new Fulton Street is now open to the public for all modes of transportation following the successful ribbon cutting ceremony on October 21, 2017. Even though our "Main Street" is back, City staff continues to work closely with American Paving Company on punch list and contract clean-up items in an effort to wrap up the construction phase. Part of that contract clean-up is the negotiation and execution of necessary contract change orders.

On August 31, 2017, Council approved Contract Change Order No. 65, which brought the apparent total contract change order amount over the delegated approval authority limit of 10% for the City Manager, per Change Order Resolution No. 2017-158. Per the resolution, all subsequent change orders which increase the contract...

Click here for full text