Title: Actions pertaining to the City of Fresno Phase 2 Regional Transmission Mains Segment B & C Project: (Council Districts 4, 5, and 7) 1. ***RESOLUTION - 48th Amendment to the Annual Appropriation Resolution No. 2017-165 to appropriate $655,000 to fund a construction contract and staff costs to construct Segments B & C of the Phase 2 Regional Transmission Mains Project (Requires 5 affirmative votes) (Subject to Mayor's veto) 2. Award a construction contract in the amount of $11,490,484 to Vido Artukovich & Son, Inc./Vidmar, Inc., a joint venture for the City of Fresno Phase 2 Regional Transmission Mains Segment B & C Project - Bid File No. 3452 (Council Districts 4, 5, and 7) 3. Authorize the Director of Public Utilities, or designee, to sign the agreement on behalf of the City
Sponsors: Department of Public Utilities
Attachments: 1. 18 48th Segments BC Reg TM SAM 12.22.17 (Attachment 1).pdf, 2. 3452BidEval (Attachment 2).pdf, 3. Sample contract (Attachment 3).pdf, 4. RTM Map (Attachment 4).pdf
REPORT TO THE CITY COUNCIL


January 11, 2018


FROM: THOMAS C. ESQUEDA, Director
Department of Public Utilities

THROUGH: MICHAEL CARBAJAL, Planning Manager
Department of Public Utilities - Utilities Planning & Engineering

BY: MARTIN WENDELS, Project Manager
Department of Public Utilities - Utilities Planning & Engineering


SUBJECT
Title

Actions pertaining to the City of Fresno Phase 2 Regional Transmission Mains Segment B & C Project: (Council Districts 4, 5, and 7)
1. ***RESOLUTION - 48th Amendment to the Annual Appropriation Resolution No. 2017-165 to appropriate $655,000 to fund a construction contract and staff costs to construct Segments B & C of the Phase 2 Regional Transmission Mains Project (Requires 5 affirmative votes) (Subject to Mayor's veto)
2. Award a construction contract in the amount of $11,490,484 to Vido Artukovich & Son, Inc./Vidmar, Inc., a joint venture for the City of Fresno Phase 2 Regional Transmission Mains Segment B & C Project - Bid File No. 3452 (Council Districts 4, 5, and 7)
3. Authorize the Director of Public Utilities, or designee, to sign the agreement on behalf of the City

Body
RECOMMENDATIONS

Staff recommends that City Council approve the 48th Amendment to the Annual Appropriation Resolution (AAR) No. 2017-165 to appropriate $655,000 to fund a construction contract and staff costs to construct Segments B & C of the Phase 2 Regional Transmission Mains Project; award a construction contract in the amount of $11,490,484 to Vido Artukovich & Son, Inc./Vidmar, Inc., a joint venture (JV), for the City of Fresno Phase 2 Regional Transmission Mains Segment B & C Project; and authorize the Director of Public Utilities, or designee, to sign the contract on behalf of the City of Fresno.

EXECUTIVE SUMMARY

On February 26, 2015, the City Council adopted a five-year water utility rate plan to finance the construction of a five-year water capital plan totaling approximately $429 million. The five-year capital plan inclu...