Fresno Logo
File #: ID18-0156    Version: 2 Name:
Type: Action Item Status: Agenda Ready
File created: 1/18/2018 In control: Planning Commission
On agenda: 2/21/2018 Final action:
Title: Consideration of Pre-zone Application No. R-17-015, Annexation Application No. ANX-17-007 and related Environmental Assessment No. R-17-015/ANX-17-007. These applications pertain to approximately a 1.86 acre site located on the north side of East Belmont Avenue between North Fowler and North Armstrong Avenues in the unincorporated portion of City's Sphere of Influence boundary (Council District 5-Chavez). 1. RECOMMEND APPROVAL (to the City Council) of the Mitigated Negative Declaration prepared for Environmental Assessment No. R-17-015/ANX-17-007 dated January 19, 2018. 2. RRECOMMEND APPROVAL (to the City Council) of Pre-zone Application No. R-17-015 which proposes to amend the Official Zone Map from the AE-20 (Ag, Exclusive 20-Acres) County of Fresno zone district to the City of Fresno BP/UGM(Business Park/Urban Growth Management) zone district consistent with the Fresno General Plan planned land use of Business Park. 3. RECOMMEND APPROVAL (to the City Council) of Annexation ...
Attachments: 1. Exhibit A Vicinity Map, 2. Exhibit B 2017 Aerial Photogragh, 3. Exhibit C Public Hearing Notice Mailing Vicinity Map, 4. Exhibit D General Plan Planned Land Uses, 5. Exhibit E Prposed Prezone and Annexation, 6. Exhibit F Project Information Tables.pdf, 7. Exhibit G Fresno Municipal Code Findings, 8. Exhibit H Environmental Assessment No. R-17-015,R-17-007, Mitigated Negative Declaration dated January 19, 2018, 9. Exhibit I Application Material

REPORT TO THE PLANNING COMMISSION

 

 

 

February 21, 2018

 

 

FROM:                     JENNIFER K. CLARK, Director

Development and Resource Management Department

 

THROUGH:                      MIKE SANCHEZ, Assistant Director

                                          Development and Resource Management Department

 

BONIQUE EMERSON, Planning Manager

                                          Development Services Division

 

BY:                                          BRUCE BARNES, Project Manager

                                          Development Services Division

 

SUBJECT

Title

Consideration of Pre-zone Application No. R-17-015, Annexation Application No. ANX-17-007 and related Environmental Assessment No. R-17-015/ANX-17-007.  These applications pertain to approximately a 1.86 acre site located on the north side of East Belmont Avenue between North Fowler and North Armstrong Avenues in the unincorporated portion of City’s Sphere of Influence boundary (Council District 5-Chavez).

 

1.                     RECOMMEND APPROVAL (to the City Council) of the Mitigated Negative Declaration prepared for Environmental Assessment No. R-17-015/ANX-17-007 dated January 19, 2018.

 

2.                     RRECOMMEND APPROVAL (to the City Council) of Pre-zone Application No. R-17-015 which proposes to amend the Official Zone Map from the AE-20 (Ag, Exclusive 20-Acres) County of Fresno zone district to the City of Fresno BP/UGM(Business Park/Urban Growth Management) zone district consistent with the Fresno General Plan planned land use of Business Park.  

 

 

3.                     RECOMMEND APPROVAL (to the City Council) of Annexation Application No. ANX-17-007, which proposes detachment of the property from the Kings River Conservation District and the Fresno County Fire Protection District and annexation to the City of Fresno. These actions are under the jurisdiction of the Local Agency Formation Commission (LAFCO).

 

 

Body

EXECUTIVE SUMMARY

Pre-zone Application No. R-17-015 and Annexation Application No. ANX-17-007 were filed by Mike Pickett, on behalf of Don Pickett and Associates, and pertain to ±1.86 acres of property located on the north side of East Belmont Avenue between North Fowler and North Armstrong Avenues in the unincorporated portion of City’s Sphere of Influence boundary.

 

Pre-zone Application No. R-17-015 proposes to amend the Official Zone Map from the AE-20 (Ag, Exclusive 20-Acres) County of Fresno zone district to the City of Fresno BP/UGM (Business Park/Urban Growth Management) zone district consistent with the Fresno General Plan planned land use.

 

Annexation Application No. ANX-17-007 proposes detachment of the property from the Fresno County Fire Protection District and the Kings River Conservation District and annexation to the City of Fresno.   NOTE:  The pre-zone only affects ±1.86 acres of private property.  However, the annexation will include 7.8 acres which includes the private property as well as the entire right-of-way for State Route 180 to the north of the private property.  The Police Department and Fire Department would like to be notified so they can respond to any vehicle accidents or fires along State Route 180.

 

Based upon analysis of the applications and subject to the applicant’s compliance with all conditions of approval, dated February 21, 2018, staff concludes that the required Rezone findings of Section 15-5812 of the Fresno Municipal Code (FMC) can be made.  These findings are attached as Exhibit G.

 

BACKGROUND / ANALYSIS

 

Mike Pickett, on behalf of Don Pickett and Associates, filed Rezone Application No. R-17-015 and Annexation Application No. ANX-17-007 which pertain to ±1.86 acres of property located on the north side of East Belmont Avenue between North Fowler and North Armstrong Avenues in the unincorporated portion of City’s Sphere of Influence boundary.

 

The subject property is a portion of unincorporated land in the County of Fresno.  Adjacent uses to the north and east include about 6 acres of State Route 180.   Adjacent uses to the west include rural residential located in the County and to the south there are several vacant light industrial parcels. 

 

Pre-zone Application No. R-17-015 proposes to amend the Official Zone Map from the AE-20 (Ag, Exclusive 20-Acres) County of Fresno zone district to the City of Fresno BP/UGM (Business Park/Urban Growth Management) zone district consistent with the Fresno General Plan planned land use of Business Park. The pre-zone of the property is for purposes of facilitating annexation pursuant to Annexation Application No. ANX-17-007, which also proposes detachment of the property from the Kings River Conservation District and the Fresno County Fire Protection District and annexation to the City of Fresno. These actions are under the jurisdiction of LAFCO.

 

At a future point the applicant intends to construct a 25,000 square foot office-warehouse building with a loading dock and approximately 35 parking stalls. The project is consistent with other Business Park and Light Industrial uses occurring to the east and south of the site.

 

Land Use Plans and Policies

 

As proposed, the project would be consistent with the Fresno General Plan goals and objectives related to Business Park land use and the urban form:

 

Objective LU-7 of the Fresno General Plan encourages the City to plan and support industrial development and to support job growth.  Objective LU7-b is intended to promote business and industrial park sites of sufficient size, unified design, and diversified in activity to attract a full range of business types needed for economic growth. The site is readily served by sewer and water with excellent access off of State Route 180 at the North Fowler Avenue off-ramp. 

 

These Objectives noted above contribute to the establishment of a comprehensive city-wide land use planning strategy to meet economic development objectives, achieve efficient and equitable use of resources and infrastructure, and create an attractive living environment in accordance with Objective LU-1 of the Fresno General Plan.

 

Policies LU-1-e and LU-1-g recommend that annexations to the City conform to the General Plan Land Use Designations and maintain the City’s current Sphere of Influence (SOI) Boundaries without additional expansion.

 

The Fresno General Plan also provides that recommendations for annexations into the City will comply with the Amended and Restated Memorandum of Understanding between the County of Fresno and the City of Fresno (MOU).  Whatever method is ultimately adopted, the City should implement an easy-to-track, objective, transparent measurement that can be used to determine the appropriate timing for allowing development in areas subject to the restrictions enumerated in the MOU for new growth. The City will use strategic phasing to achieve the overall goals of the plan, as opposed to annual limits of some sort that place unrealistic controls on the local market.  For this purpose, the Implementation element of the General Plan includes Strategic Sequencing of Development.

 

The proposed annexation is consistent with the adopted sphere of influence and does not conflict with the goals and/or policies of the Cortese-Knox-Hertzberg Local Government Reorganization Act of 2000. The proposal is consistent with the City General and Community plans, including adopted goals and policies.

 

Furthermore, as referenced herein above, the subject properties proposed for annexation will be compliant with the MOU standards for annexation by meeting the minimum requirements for consideration under the provisions for existing substantial development and the creation of logical boundaries.  Finally, the proposal for annexation is presumed to comply with all standards for annexation as it removes a portion of an unincorporated area that is partially surrounded by the incorporated city.  Future development of property proposed to be annexed will fully fund public facilities and infrastructure as necessary to mitigate any impacts arising from the new development. The development project will pay for public facilities and infrastructure improvements in proportion to the development’s neighborhood and citywide impacts. The development will fully fund ongoing public facility and infrastructure maintenance and public service costs.

 

Therefore, it is staff’s opinion that the proposed project is consistent with respective general and community plan objectives and policies and will not conflict with any applicable land use plan, policy or regulation of the City of Fresno.  Furthermore, the proposed project, including the design and improvement of the subject property, is found; (1) to be consistent with the goals, objectives and policies of the applicable Fresno General Plan, McLane Community Plan and Fresno Yosemite International Airport Plan; (2) to be suitable for the type and density of development; (3) to be safe from potential cause or introduction of serious public health problems; and, (4) to not conflict with any public interests in the subject property or adjacent lands.

 

Public Resources

Evaluation of public services capacity and availability for the area has determined that public infrastructure improvements exist within the surrounding area to serve existing development within the vicinity as well as future development on the subject properties.  Furthermore, the proposed project will be obligated to pay fair share and proportional payment of fees and all development mitigation costs.  The Department of Public Utilities (DPU) has determined that adequate sanitary sewer and water services are available to serve the project site subject to implementation of the Fresno General Plan policies and mitigation measures of the related MEIR and the construction and installation of public facilities and infrastructure in accordance with Department of Public Works standards, specifications and policies.

 

Review for compliance with fire and life safety requirements for the interior of proposed buildings and the intended use are reviewed by both the Fire Department and the Building and Safety Services Section of the Development and Resource Management Department when a submittal for building plan review is made as required by the California Building Code.

 

The Fresno Metropolitan Flood Control District (FMFCD) has indicated that the subject annexation boundary encompasses lands within the FMFCD and will be served by the District’s Storm Drainage and Flood Control Master Plan.

 

 

Circulation Element Plan Policies and Major Street System Traffic Capacity

The Fresno General Plan designates East Belmont Avenue as an arterial street. The developer of this project will be required to dedicate and construct improvements along the major street frontage with future development.

 

The Public Works Department, Traffic Engineering Division has reviewed the potential traffic related impacts for the proposed project and has determine the streets adjacent to and near the subject site will be able to accommodate the quantity and kind of traffic which may be potentially generated subject to City requirements.  These requirements generally include: (1) The provision of a minimum two points of vehicular access to major streets for any phase of the development; (2) Major street dedication; (3) Street improvements, (including, but not limited to, construction of concrete curbs, gutters, pavement, underground street lighting systems; and, (4) Payment of applicable impact fees (including, but not limited to, the Traffic Signal Mitigation Impact (TSMI) Fee, Fresno Major Street Impact (FMSI) Fee, and the Regional Transportation Mitigation Fee (RTMF) Fee.  

 

The area street plans are the product of careful planning that projects traffic capacity needs based on the densities and intensities of planned land uses anticipated at build-out of the planned area.  Based upon the project requirements for street dedications, improvements, and contributions to the City wide impact fee system, the adjacent and interior streets will provide adequate access to, and recognize the traffic generating characteristics of, individual properties and, at the same time, afford the community an adequate and efficient circulation system.

 

Council District Plan Implementation Committee

 

The District 5 Plan Implementation Committee met on January 22, 2018 and unanimously voted to recommend approval of the pre-zone and annexation. 

 

Notice of Planning Commission Hearing

 

The Development and Resource Management Department mailed notices of this Planning Commission hearing to surrounding property owners within 1,000 feet of the subject property.

 

ENVIRONMENTAL FINDING

 

An environmental assessment was prepared for this project in accordance with the requirements of the California Environmental Quality Act (CEQA) Guidelines.  This process included the distribution of requests for comment from other responsible or affected agencies and interested organizations.

 

Preparation of the environmental assessment necessitated a thorough review of the proposed project and relevant environmental issues and considered previously prepared environmental and technical studies pertinent to the area, including the Fresno General Plan Master Environmental Impact Report (MEIR SCH No. 2012111015).  These environmental and technical studies have examined projected sewage generation rates of planned urban uses, the capacity of existing sanitary sewer collection and treatment facilities, and optimum alternatives for increasing capacities; groundwater aquifer resource conditions; water supply production and distribution system capacities; traffic carrying capacity of the planned major street system; and, student generation projections and school facility site location identification.

 

The City of Fresno has conducted an initial study of the above-described project and it has been determined to NOT be a subsequent project that is fully within the scope of the MEIR SCH No. 2012111015, which was prepared for the Fresno General Plan and adopted by the Fresno City Council on December 18, 2014.  Therefore, the Development and Resource Management Department proposes to adopt a Mitigated Negative Declaration for this project.

 

With mitigation imposed, there is no substantial evidence in the record that this project may have additional significant, direct, indirect or cumulative effects on the environment that are significant and that were not identified and analyzed in the MEIR.  After conducting a review of the adequacy of the MEIR pursuant to Public Resources Code, Section 21157.6(b)(1), the Development and Resource Management Department, as lead agency, finds that no substantial changes have occurred with respect to the circumstances under which the MEIR was certified and that no new information, which was not known and could not have been known at the time that the MEIR was certified as complete has become available.  The project is not located on a site which is included on any of the lists enumerated under Section 65962.5 of the Government Code including, but not limited to, lists of hazardous waste facilities, land designated as hazardous waste property, hazardous waste disposal sites and others, and the information in the Hazardous Waste and Substances Statement required under subdivision (f) of that Section. A public notice for Environmental Assessment No. R-17-015/ANX-17-007 was published on January 19, 2018 with no comments or appeals received to date.

 

FRESNO MUNICIPAL CODE FINDINGS

 

Based upon analysis of the applications, staff concludes that the required findings of Section 15-5812 of the FMC can be made.  These findings are attached as Exhibit G to this staff report. 

 

CONCLUSION

The appropriateness of the proposed project has been examined with respect to its consistency with goals and policies of the Fresno General Plan, the McLane Community Plan and the Fresno Yosemite International Airport Plan; its compatibility with surrounding uses; and its avoidance or mitigation of potentially significant adverse environmental impacts.  These factors have been evaluated as described above and by the accompanying environmental assessment.  Upon consideration of this evaluation, it can be concluded that Pre-zone Application No. R-17-015 and Annexation Application No. ANX-17-007 are appropriate for the project site; and, that all criteria identified within Articles 53, 58 and 61 of Chapter 15 of the FMC have been met.

 

 Attachments:                    

 

Exhibit A:                                          Vicinity Map

Exhibit B:                                          Aerial Photograph

Exhibit C:                                          Public Hearing Notice Mailing List Vicinity Map

Exhibit D:                                          Fresno General Plan Planned Land Use Map

Exhibit E:                                          Proposed Pre-zone and Annexation Map

Exhibit F:                                          Project Information Tables

Exhibit G:                                         Fresno Municipal Code Findings

Exhibit H                     Environmental Assessment No.R-17-007/ANX-17-015, Mitigated Negative Declaration dated January 19, 2018

Exhibit I                     Application Material