File #: ID18-0260    Version: 1 Name:
Type: Action Item Status: Passed
File created: 2/9/2018 In control: City Council
On agenda: 3/1/2018 Final action: 3/1/2018
Title: Approve a substitution of a listed Subcontractor Tennyson Electric, Inc., for the Fairview Trail Rehabilitation Project ID PW00759 (Council District 3)
Sponsors: Public Works Department
Attachments: 1. 18-0260 Contractor's Request for Substitution Letter.pdf, 2. 18-0260 Administrative Hearing Officer's Recommendation.pdf
REPORT TO THE CITY COUNCIL


March 1, 2018


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: ROBERT N. ANDERSEN, PE, Assistant Director
Public Works Department

BILL HERR, Construction Manager
Public Works Department, Construction Management Division

SUBJECT
Title
Approve a substitution of a listed Subcontractor Tennyson Electric, Inc., for the Fairview Trail Rehabilitation Project ID PW00759 (Council District 3)

Body
RECOMMENDATION

It is recommended that the City Council approve the request from Frank Loduca Construction Inc., and the recommendation from City of Fresno Administrative Hearing Office Michael Flores, to substitute Tennyson Electric Inc., of Livermore, California, and utilize Underground Specialties Central Coast, Inc., of Templeton, California for the electrical portion of this project.

EXECUTIVE SUMMARY

Frank Loduca Construction Inc., (Loduca), the General Contractor who was awarded the referenced project, has requested to substitute Tennyson Electric Inc., of Livermore, California (Tennyson) who is listed in the bid documents as performing the electrical work for the project. In accordance with the bid documents, Loduca listed Tennyson because the work exceeds one-half of one percent of the total contract amount. Loduca notified the City by a letter dated November 20, 2017, that their Subcontractor, Tennyson, after having a reasonable opportunity to do so, has failed or refused to execute a written subcontract. Loduca is asking that they be allowed to use Underground Specialties Central Coast Inc., of Templeton, California (USCC), to perform the electrical work portion of the project. This action requires Council approval because Public Contract Code Section 4107 requires consent of the awarding authority to a request by a prime contractor for a substitution of a subcontractor.

BACKGROUND

On June 22, 2017, a contract was awarded in the amount of $484,010 to Loduca for the Fairview Trail Rehabilitation ...