File #: ID18-0264    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 2/9/2018 In control: City Council
On agenda: 3/1/2018 Final action:
Title: Approve Amendment No. 3 to the Copper River Ranch Water Supply Implementation Agreement approved by Fresno City Council on November 17, 2016 (Council District 6)
Sponsors: Department of Public Utilities
Attachments: 1. 2018-03-01 CRR Amendment 3.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REPORT TO THE CITY COUNCIL

 

 

March 22, 2018

 

 

FROM:                     THOMAS C. ESQUEDA, Director

Department of Public Utilities

 

SUBJECT

Title

 

Approve Amendment No. 3 to the Copper River Ranch Water Supply Implementation Agreement approved by Fresno City Council on November 17, 2016  (Council District 6)

 

Body

RECOMMENDATION

The Administration recommends the City Council approve Amendment No. 3 to the Copper River Ranch Water Supply Implementation Agreement (Agreement) for the Developers of the Copper River Ranch Development (Copper River or the Project Area).  Amendment No. 3 is provided for the convenience of the Developers to address default conditions caused by the Developers’ failure to timely fulfill the obligations required by the Agreement.  In exchange for an extension to complete the construction of certain water supply facilities, the Developer has agreed to pay $567,623.50, which is the remaining balance due on the Developer’s Development Fee obligation.  Developer shall make the final payment by March 2, 2018.

 

EXECUTIVE SUMMARY

On November 17, 2016, the Fresno City Council approved the Agreement with the Developers of the Copper River Ranch Development (Developer) to provide 4,900 GPM of firm water supply capacity within the Project Area in accordance with a mutually-agreed upon project completion schedule.  The Agreement also included a payment schedule whereby Developer is to pay City a total of approximately $3.8 million for Developer’s proportionate share of the cost of connecting the Project Area to the City’s existing water system, including the Northeast Surface Water Treatment Facility (NESWTF).  The signatory parties for the Developer are Mr. Darius Assemi and Mr. Gary McDonald.

On March 1, 2017, Developer defaulted on certain water supply construction obligations under the Agreement.  In response to a notice of default, Developer requested an amendment to the Agreement for a one time extension to fulfill project conditions.  In exchange, Developer has agreed to accelerate payment of a portion of the $3.8 million proportionate share reimbursement due to City.

On August 1, 2017, Developer defaulted again on certain water supply construction obligations under the Agreement.  In response to the default condition, Developer requested a second amendment to the Agreement for a second time extension to fulfill project conditions.  In exchange, Developer has agreed to pay $700,000.00 of its remaining $1,267,623.50 Development Fee obligation, and Developer was to pay the final remaining balance of $567,623.50 by December 1, 2018.

On December 1, 2018, Developer defaulted again on certain water supply construction obligations under the Agreement.  In response to the default condition, Developer requested a third amendment to the Agreement for a third time extension to fulfill project conditions.  In exchange for an extension to complete the construction of certain water supply facilities, the Developer shall pay $567,623.50, which is the remaining balance due on the Developer’s Development Fee obligation.  Developer shall make the final payment by March 2, 2018.

 

The Administration recommends City Council approve Amendment No. 3 to the Agreement, which extends timelines to complete agreed upon water supply improvements and completes payment of Developer’s Development Fee obligation.

BACKGROUND

On November 16, 2017, City staff met with the Developers to discuss the completion status for water supply projects required as a condition of the Agreement, the City’s right to cease issuance of certificates of occupancy within the Project Area due to a default condition), and the path forward options in the event a third default condition occurred.

On December 1, 2017, Developer defaulted on its obligations under the Agreement by failing to timely construct and to complete the required work for PS 330, PS 370, and the Manganese Disposal Line.  Upon entering into a 3rd default condition, the Developer has requested that the City provide a third extension of time to allow Developer to complete the required water supply projects.  After consulting with the Developer about the third default condition, the City has agreed to provide the Developer with a reasonable opportunity to cure the default by modifying the completion schedule for projects and payments required by the Agreement.  For the convenience of the Developer, the City agrees to modify the implementation schedule with Amendment No. 3 to the Water Supply Implementation Agreement as follows:

Milestone Requirement

Originally Agreed Upon Completion Date

New Required Completion Date

Increase Capacity of PS 330 from 1,200 gpm to 1,800 gpm

March 1, 2017

June 1, 2018

New PS 369 (minimum capacity 1,000 gpm)

March 1, 2017

Complete

New PS 370 (minimum capacity 500 gpm)

June 30, 2017

June 1, 2018

New PS 371 (minimum capacity 500 gpm)

December 1, 2018

December 1, 2018

Mn Discharge Pipeline for PS 330, 369, 370, and 371

March 1, 2017

June 1, 2018

1st Payment Developer Fee Obligation

December 17, 2017

Paid

2nd Payment Developer Fee Obligation

June 30, 2017

Paid

3rd Payment (1st Installment) Developer Fee Obligation

December 1, 2018

Paid

3rd Payment (2nd Installment) Developer Fee Obligation

December 1, 2018

March 2, 2018

 

The City’s Administration has authorized the continued issuance of certificates of occupancy for lots within the Project Area until such time that the Fresno City Council considers Amendment No. 3.  Should the Fresno City Council not approve Amendment No. 3 to the Agreement, the Administration will discontinue issuing certificates of occupancy in the Project Area effective 8:00 am on Friday, March 2, 2018.

All other terms and conditions of the Agreement shall remain in effect.  However, by entering into Amendment No. 3, the Developer acknowledges and agrees to voluntarily refrain from submitting any development applications, tentative tract maps, or similar related to the Project Area until the obligations of this Agreement have been satisfied.  Further, the City shall at all times retain the right to cease issuing building permits and certificates of occupancy for any lots within the Project Area if a 4th default condition occurs.  The City’s obligation for a 4rd default condition caused by the Developer will be to notify the Developer in writing that the City will cease issuing building permits and certificates of occupancy on the first working day after an obligation has not been fulfilled.

Amendment No. 3 to the Agreement has been approved as to form by the City Attorney.

ENVIRONMENTAL FINDINGS

Pursuant to CEQA Guidelines section 15378(b)(5), this is not a project for the purpose of CEQA, as this is an organizational or administrative action of the government to enforce an existing obligation, and will not result in a direct or indirect physical change in the environment.

LOCAL PREFERENCE

Local preference was not considered because this Agreement regarding water supply infrastructure development does not include a bid or award of a construction or services contract.

FISCAL IMPACT

There is no financial obligation for the General Fund for this Agreement.  The payment of $4,291,300 to be made by the Developers will be received into the Water Division Enterprise Fund to benefit the expansion and upgrade of the City’s NESWTF, and to secure adequate water supply capacity, reliability, and redundancy for area served by the NESWTF.

 

Attachment:

Third Amendment to the Copper River Ranch Water Supply Implementation Agreement