File #: ID18-0620    Version: 1 Name:
Type: Discussion Item Status: Passed
File created: 5/8/2018 In control: City Council
On agenda: 5/24/2018 Final action: 5/24/2018
Title: Actions pertaining to Fire Station No. 20 remodel project located in the Fig Garden Fire Protection District 1. Adopt a finding of Categorical Exemption per staff determination, pursuant to Section 153-1(a) of the California Environmental Quality Act Guidelines 2. ***RESOLUTION - 69th Amendment to the Annual Appropriation Resolution (AAR) No. 2017-165 appropriating $169,600 for completion of the Fire Station No. 20 remodel (Requires 5 affirmative votes) (Subject to Mayor veto)
Sponsors: Fire Department
Attachments: 1. 18 69th FS 20.PR.pdf
REPORT TO THE CITY COUNCIL


May 24, 2018


FROM: KERRI L. DONIS, Fire Chief
Fresno Fire Department

SUBJECT
Title
Actions pertaining to Fire Station No. 20 remodel project located in the Fig Garden Fire Protection District
1. Adopt a finding of Categorical Exemption per staff determination, pursuant to Section 153-1(a) of the California Environmental Quality Act Guidelines
2. ***RESOLUTION - 69th Amendment to the Annual Appropriation Resolution (AAR) No. 2017-165 appropriating $169,600 for completion of the Fire Station No. 20 remodel (Requires 5 affirmative votes) (Subject to Mayor veto)

Body
RECOMMENDATIONS

Staff recommends that Council adopt the 69th Amendment to the AAR No. 2017-165 which provides for the following: Appropriations in the amount of $25,000 for project change orders approved by the Fig Garden Fire Protection District (District), and appropriations in the amount of $144,600 due to timing of the project crossing fiscal years.

EXECUTIVE SUMMARY

The remodel of Fire Station No. 20 is fully funded by the District. The project was approved by the District in late fiscal year 2017. In May 2017, the District transferred $887,100 to the City and the funds were appropriated on May 11, 2017, via Council resolution (52nd amendment to the AAR No. 2016-118). Due to timing, the remodel project crossed fiscal years making it necessary to re-appropriate funds not utilized in the prior fiscal year.

BACKGROUND

In May 2017 the District transferred $887,100 to the City for the remodel of Fire Station #20. Council approved the 52nd amendment to the Annual Appropriation Resolution (AAR) 2016-118 appropriating $887,100 for the project, including a contract award to DivCom Construction, Inc., in the amount of $742,039 and another $145,061 for construction management, project management, permits, and other charges to be incurred by the Department of Public Works as Project Manager.

The remodel project overlapped fiscal years with the majority of...