SUBJECT
...Title
Actions pertaining to the Sugar Pine Trail Park and Ride Project at the southwest corner of Willow Avenue and Shepherd Avenue - Bid File No. 3664 (Council District 6)
1. Adopt a finding of Categorical Exemption per staff determination, pursuant to Section 15303 Class 3, Section 15311 Class 11 (b) and Section 15332 Class 32 of the California Environmental Quality Act guidelines for the Sugar Pine Trail Park and Ride Project at the southwest corner of Willow Avenue and Shepherd Avenue
2. Award a construction contract in the amount of $423,576.00 to Dave Christian Construction Inc., of Fresno, California for the Sugar Pine Trail Park and Ride Project at the southwest corner of Willow Avenue and Shepherd Avenue
...Body
RECOMMENDATIONS
Staff recommends that the City Council adopt a finding of Categorical Exemption pursuant to Section 15303 Class 3, Section 15311 Class 11 (b) and 15332 Class 32 of the California Environmental Quality Act (CEQA) guidelines, award a construction contract for the Sugar Pine Trail Park and Ride Project with Dave Christian Construction Inc. of Fresno, California in the amount of $423,576.00 as the lowest responsive and responsible bidder and authorize the Public Works Director or designee to sign the construction contract on behalf of the City of Fresno.
EXECUTIVE SUMMARY
The City of Fresno seeks to construct the Sugar Pine Trail Park and Ride Project at the southwest corner of Willow Avenue and Shepherd Avenue on a city owned parcel. The scope of work includes street widening and sidewalk the souths side of Shepherd Avenue along the park and ride frontage, install striping and pavement markings, replacement of traffi...
Click here for full text