File #: ID19-11628    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 11/22/2019 In control: City Council
On agenda: 12/12/2019 Final action: 12/12/2019
Title: Approve a Ninth Amendment to Reimbursement Agreement No. HSR 11-29 with the California High Speed Rail Authority (CHSRA), for the purposes of extending the contract end date by 36 months to December 31, 2022, and increasing the agreement amount by $508,000 for a total of $1,929,000 (Council Districts 1, 2, & 3).
Sponsors: Public Works Department
Attachments: 1. 19-11628 Standard Agreement Amendment No 9, 2. 19-11628 Standard Agreement HSR 11-29, 3. 19-11628 Vicinity Map
REPORT TO THE CITY COUNCIL


December 12, 2019


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

THROUGH: ANDREW J. BENELLI, PE, City Engineer/Assistant Director
Public Works Department, Traffic Operations and Planning Division

BY: JESUS AVITIA, Deputy City Engineer
Public Works Department, Traffic Operations and Planning Division

SUBJECT
Title
Approve a Ninth Amendment to Reimbursement Agreement No. HSR 11-29 with the California High Speed Rail Authority (CHSRA), for the purposes of extending the contract end date by 36 months to December 31, 2022, and increasing the agreement amount by $508,000 for a total of $1,929,000 (Council Districts 1, 2, & 3).
Body

RECOMMENDATIONS

Staff recommends the Council authorize the Public Works Director or his designee to execute the Ninth Amendment to the California High Speed Rail Authority (CHSRA) Reimbursement Agreement No. HSR 11-29 to extend the contract term by 36 months to December 31, 2022 and increase the agreement amount by $508,000 (the Ninth Amendment); and authorize the Public Works Director to execute the amendment on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The Ninth Amendment will extend the term of CHSRA Reimbursement Agreement No. HSR 11-29 (the Agreement) by 36 months, with the new contract end date of December 31, 2022, and will increase the total contract amount by $508,000 to $1,929,000. The amendment will provide for continued reimbursement for the cost of staff services to continue working on new and existing cooperative agreements and right of way functions required for the High Speed Rail program. Staff will be preparing and reviewing legal descriptions, mapping for Right of Entry, Joint Use Agreements (JUA), Consent for Common Use Agreements (CCUA), Vacations, and dedication packages.

BACKGROUND

On May 3, 2012, Council approved a Memorandum of Understanding with the CHSRA to develop a series a Cooperative Agreements for the High Speed Rail Project. The CHSRA ...

Click here for full text