REPORT TO THE CITY COUNCIL
February 27, 2020
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
TJ MILLER, Interim Director
Parks, After School, Recreation & Community Services Department
THROUGH: WILLIAM C. HERR, Assistant Director
Public Works Department, Facilities and Construction Management Divisions
BY: DEBBIE BERNARD, Project Manager
Public Works Department, Facilities Management Division
SUBJECTS
Title
Approve an agreement with LDA Partners of Stockton, CA in the amount of $765,000 with a contingency amount not to exceed $35,000 for the master plan and design of plans, cost estimates, general construction documents, bidding assistance, and contract administration for the Multi-Generational Center project at C.W. Large Park. (Council District 4)
Body
RECOMMENDATIONS
Staff is recommending that Council approve a consultant agreement with LDA Partners of Stockton, CA in the amount of $765,000 with a contingency amount not to exceed $35,000 for the master plan and design of construction documents for the Multi-Generational Center at C.W. Large Park and authorize the Public Works Director or designee to sign the standardized agreement on behalf of the City.
EXECUTIVE SUMMARY
Council District 4 is in need of a community center to serve both seniors and youth. C.W. Large Park is located on Millbrook Avenue between Ashlan and Gettysburg Avenues and is currently an open green space park with no recreation facilities. The Multi-Generational Center will not only provide a space for seniors and youth to go for recreation but also receive the benefits of various Parks, After School, Recreation and Community Services (PARCS) programs. Staff recommends that Council approve a consultant agreement with LDA Partners to develop a master plan and construction documents to construct the Multi-Generational Center.
BACKGROUND
C.W. Large Park is located at 4424 N. Millbrook Avenue between Ashlan and Gettysburg Avenues. ...