File #: ID 20-00435    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 3/24/2020 In control: City Council
On agenda: 4/9/2020 Final action: 4/9/2020
Title: Approve the First Amendment to the Professional Consultant Services Agreement with Blair, Church & Flynn Consulting Engineers, Inc., to extend the work completion date from December 20, 2019 to November 1, 2020, for the preparation of plans and specifications for construction of the Congo Alley Water Main Replacement Project, for a previously approved contract amount of $35,800. (Council District 3)
Sponsors: Department of Public Utilities
Attachments: 1. Attachment 1 - First Amendment to Agreement.pdf, 2. Attachment 2 - Original Consultant Agreement.pdf
REPORT TO THE CITY COUNCIL


April 9, 2020


FROM: MICHAEL CARBAJAL, Director
Department of Public Utilities

THROUGH: BROCK D. BUCHE, PE, PLS, Assistant Director - UP&E
Department of Public Utilities - Utilities Planning & Engineering

BY: ROBERT A. DIAZ, Supervising Engineering Technician
Department of Public Utilities - Utilities Planning & Engineering

SUBJECT
Title

Approve the First Amendment to the Professional Consultant Services Agreement with Blair, Church & Flynn Consulting Engineers, Inc., to extend the work completion date from December 20, 2019 to November 1, 2020, for the preparation of plans and specifications for construction of the Congo Alley Water Main Replacement Project, for a previously approved contract amount of $35,800. (Council District 3)

Body
RECOMMENDATIONS

Staff recommends that City Council approve the First Amendment to Professional Consultant Services Agreement (Agreement), to extend the duration of the Agreement from December 20, 2019 to November 1, 2020, for the preparation of plans and specifications for the construction of the Congo Alley Water Main Replacement Project (Project), and authorize the Director of Public Utilities, or designee, to sign the Amendment on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

On December 20, 2018, the City entered into an Agreement with Consultant in the amount of $35,800 for the preparation of plans and specifications for construction of the Project. Due to the lengthy amount of time expended to secure a key pipeline easement, the Agreement needs to be extended to retain the Consultant's services through the completion of the project. This Amendment will extend the Agreement completion date to November 1, 2020. The current contract amount of $35,800 will remain the same with this Amendment.

BACKGROUND

The Department of Public Utilities, Water Division has identified approximately 500 linear feet of 12-inch cast iron water main located in Congo Alley, between Fres...