Fresno Logo
File #: ID 20-00482    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 4/8/2020 In control: City Council
On agenda: 4/23/2020 Final action: 4/23/2020
Title: Approve the Fourth Amendment to the Professional Consultant Services Agreement with Blair, Church, & Flynn Consulting Engineers, Inc., to extend the Agreement from August 31, 2019 to May 31, 2020, for the City of Fresno's Phase 2 Regional Transmission Mains, for the previously approved contract amount of $3,836,191 (Council Districts 1, 3, 4, 5, and 7, County of Fresno)
Sponsors: Department of Public Utilities
Attachments: 1. Attachment 1- Fourth Amendment to Agreement.pdf, 2. Attachment 2- Original Agreement, First, Second, and Third Amendment.pdf
REPORT TO THE CITY COUNCIL


April 23, 2020


FROM: MICHAEL CARBAJAL, Director
Department of Public Utilities

THROUGH: BROCK D. BUCHE, PE, PLS, Assistant Director - UP&E
Department of Public Utilities - Utilities Planning & Engineering

BY: MARTIN WENDELS, Project Manager
Department of Public Utilities - Water Division

SUBJECT
Title
Approve the Fourth Amendment to the Professional Consultant Services Agreement with Blair, Church, & Flynn Consulting Engineers, Inc., to extend the Agreement from August 31, 2019 to May 31, 2020, for the City of Fresno's Phase 2 Regional Transmission Mains, for the previously approved contract amount of $3,836,191 (Council Districts 1, 3, 4, 5, and 7, County of Fresno)

Body
RECOMMENDATIONS

Staff recommends that City Council approve the Fourth Amendment to the Professional Consultant Services Agreement with Blair, Church, & Flynn Consulting Engineers (BC&F), to extend the duration of the Agreement from August 31, 2019 to May 31, 2020, for the Phase 2 Regional Transmission Mains Project (Project), and authorize the Director of Public Utilities, or designee, to sign the Amendment on behalf of the City.

EXECUTIVE SUMMARY

On June 11, 2015, the City Council approved an Agreement with BC&F to provide Professional Engineering Consultant Services for the Final Design of the City of Fresno's Phase 2 Regional Transmission Mains for a total fee of $2,836,195. On September 1, 2016, the City Council approved a First Amendment to modify the Scope of Services and increase compensation by $999,996, adjusting the contract amount to $3,836,191. On November 1, 2016, a Second Amendment was executed to extend the completion time to June 30, 2018, and a Third Amendment was executed on March 14, 2019, to extend to contract time to August 31, 2019. The Fourth Amendment to extend the contract time to May 31, 2020 is needed for the Consultant to prepare the final as-built drawings. This Project distributes treated surface water from the ...

Click here for full text