Fresno Logo
File #: ID 20-001026    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 8/5/2020 In control: City Council
On agenda: 8/20/2020 Final action: 8/20/2020
Title: Approve a Third Amendment to the Consultant Services Agreement with SDI Presence LLC., to extend the completion date to December 31, 2020, for a previously approved contract in the amount not to exceed $130,000.
Sponsors: Information Services Department
Attachments: 1. SDI Consultant Services Agreement_EXECUTED, 2. SDI 1st Amendment ERP RFP_EXECUTED, 3. SDI 2nd Amendment_EXECUTED, 4. SDI 3rd Amendment_SIGNED
REPORT TO THE CITY COUNCIL


August 20, 2020


FROM: BRYON HORN, Chief Information Officer
Information Services Department

BY: DENNIS JONES, Systems & Applications Manager
Information Services Department


SUBJECT
Title
Approve a Third Amendment to the Consultant Services Agreement with SDI Presence LLC., to extend the completion date to December 31, 2020, for a previously approved contract in the amount not to exceed $130,000.

Body
RECOMMENDATION

Staff recommends Council approve the Third Amendment to the Consultant Services Agreement with SDI Presence LLC., (SDI) to extend the completion date to December 31, 2020 and authorize the Chief Information Officer or designee to execute the Third Amendment. This Amendment does not increase the contract amount, it is only an extension of time.

EXECUTIVE SUMMARY

On May 18, 2018, the City entered into a Consultant Services Agreement (Agreement) with SDI in an amount not to exceed $130,000 for assistance in assessing and creating an RFP to upgrade or replace its PeopleSoft Financial and HRMS software systems.

Having completed the competitive bid process as of July 2, 2019, City and SDI began the process of reviewing and evaluating the responses. Due to the number and complexity of the responses received, the evaluation and review process was extended to ensure a proper solution could be chosen. The contract was increased by $10,000 and the term of the Agreement extended to September 1, 2020, to allow for a thorough and comprehensive evaluation and selection process.

Since this is a very crucial selection for the City, the team has taken extra time to ensure that the solution that is chosen meets the City's needs. Being a complex project and due to the recent COVID-19 outbreak, ISD is requesting to extend the contract with SDI to December 31, 2020. We anticipate making a selection and presenting to Council in the fall.


BACKGROUND

On December 29, 2017, the City of Fresno released RFP Bid File 3595 for Con...

Click here for full text