Fresno Logo
File #: ID 21-313    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 2/17/2021 In control: City Council
On agenda: 3/4/2021 Final action: 3/4/2021
Title: Actions pertaining to the Recycled Water Distribution System Extension to the Martin Luther King Activity Center Project (Bid File 3698) (Council District 3): 1. Adopt Addendum 3 to the Fresno Recycled Water Distribution System, Southwest Quadrant Tiered Mitigated Negative Declaration (State Clearinghouse No. 2014081078) 2. Approve a Cost Reimbursement Agreement between the City of Fresno and the State Center Community College District 3. Approve the Second Amendment to the Consultant Services Agreement with Blair, Church & Flynn Consulting Engineers to increase the design fee by $58,083, for a total amended not to exceed fee of $253,053, including the contingency of $10,000, and to extend the agreement term from July 30, 2021 to February 25, 2022 4. Award a construction contract to Emmett's Excavation, Inc., in the amount of $2,822,054
Sponsors: Department of Public Utilities
Attachments: 1. Attachment 1 - Addendum 3 to the Tiered MND.pdf, 2. Attachment 2 - Cost Reimbursement Agreement.pdf, 3. Attachment 3- Second Amendment to Agreement.pdf, 4. Attachment 4 - Bid Evaluation and Fiscal Impact Statement.pdf, 5. Attachment 5 - Sample Contract.pdf, 6. Attachment 6 - Vicinity Map.pdf
REPORT TO THE CITY COUNCIL


March 4, 2021


FROM: MICHAEL CARBAJAL, Director
Department of Public Utilities

THROUGH: BROCK D. BUCHE, PE, PLS, Assistant Director - UP&E
Department of Public Utilities - Utilities Planning & Engineering

BY: PATRICIA DIEP, Supervising Engineering Technician
Department of Public Utilities - Utilities Planning & Engineering

SUBJECT
Title

Actions pertaining to the Recycled Water Distribution System Extension to the Martin Luther King Activity Center Project (Bid File 3698) (Council District 3):
1. Adopt Addendum 3 to the Fresno Recycled Water Distribution System, Southwest Quadrant Tiered Mitigated Negative Declaration (State Clearinghouse No. 2014081078)
2. Approve a Cost Reimbursement Agreement between the City of Fresno and the State Center Community College District
3. Approve the Second Amendment to the Consultant Services Agreement with Blair, Church & Flynn Consulting Engineers to increase the design fee by $58,083, for a total amended not to exceed fee of $253,053, including the contingency of $10,000, and to extend the agreement term from July 30, 2021 to February 25, 2022
4. Award a construction contract to Emmett's Excavation, Inc., in the amount of $2,822,054

Body
RECOMMENDATIONS

Staff recommends that City Council adopt Addendum 3 to the Fresno Recycled Water Distribution System (RWDS), Southwest Quadrant Tiered Mitigated Negative Declaration (MND) for the Recycled Water Distribution System (RWDS) Extension to the Martin Luther King (MLK) Activity Center Project (Project); approve a Cost Reimbursement Agreement between the City of Fresno (City) and State Center Community College District (College District); approve the Second Amendment to the Consultant Services Agreement with Blair, Church & Flynn Consulting Engineers (Consultant) for additional scope of services during construction for an increase in compensation of $58,083, resulting in a total fee amount increasing from $194,970 to $253,053, including ...

Click here for full text