Fresno Logo
File #: ID 21-764    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 10/20/2021 In control: City Council
On agenda: 11/4/2021 Final action:
Title: Actions pertaining to North Avenue sewer trunk main realignment (Bid File 3699) (Council Districts 3 and 5): 1. Adopt a finding of Categorical Exemption pursuant to Sections 15302(c) and 15303 of the California Environmental Quality Act Guidelines 2. Award a construction contract to Emmett's Excavation, Inc., of Clovis, California, in the amount of $6,372,238
Sponsors: Department of Public Utilities
Attachments: 1. Attachment 1 - Bid Evalutation and Fiscal Impact Statement.pdf, 2. Attachment 2 - Sample Contract.pdf, 3. Attachment 3 - Vicinity Map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REPORT TO THE CITY COUNCIL


November 4, 2021


FROM: MICHAEL CARBAJAL, Director
Department of Public Utilities

BY: BROCK D. BUCHE, PE, PLS, Assistant Director
Department of Public Utilities - Utilities Planning & Engineering


SUBJECT
Title

Actions pertaining to North Avenue sewer trunk main realignment (Bid File 3699) (Council Districts 3 and 5):
1. Adopt a finding of Categorical Exemption pursuant to Sections 15302(c) and 15303 of the California Environmental Quality Act Guidelines
2. Award a construction contract to Emmett's Excavation, Inc., of Clovis, California, in the amount of $6,372,238

Body
RECOMMENDATIONS

Staff recommends that City Council adopt a finding of Categorical Exemption pursuant to Sections 15302 and 15303 of the California Environmental Quality Act (CEQA) Guidelines for the North Avenue sewer trunk main realignment (Project); award a construction contract for the Project to Emmett's Excavation, Inc., in the amount of $6,372,238; and authorize the Director of Public Utilities, or designee, to sign and execute all documents on behalf of the City of Fresno (City).

EXECUTIVE SUMMARY

Structural instability of the existing sewer pipe requires the main be replaced. The discovery of a sink hole by Fresno Irrigation District staff, was determined to be the result of the failure of a section of the large diameter sewer main. Closed-Circuit Television (CCTV) inspection found the condition of this section of sewer trunk main to be structurally deficient and unable to support a point repair. This section of the sewer trunk main must be replaced in a new alignment to divert flows away from the existing sewer pipe which has deteriorated from hydrogen sulfide gas corrosion. The Department of Public Utilities (DPU), Wastewater Management Division (WMD), is seeking to award a construction contract for the Project to Emmett's Excavation, Inc., in the amount of $6,372,238.

BACKGROUND

The existing sewer trunk main in North Avenue conveys an...